Informs of Completed Installation of Third Phase of Permanent Improved Fire Detection & Protection Sys & Permanent Alternate Cooling Method
ML19261D517
Person / Time
Site: Fort Saint Vrain 
Issue date: 06/14/1979
From: Swart F
PUBLIC SERVICE CO. OF COLORADO
To: Speis T
Office of Nuclear Reactor Regulation
References
P-79129, NUDOCS 7906190395
Download: ML19261D517 (1)


Text

public service company =e cracaso i

i June 14, 1979 Fort St. Vrain Unit No. 1 P-79129 Mr. Themis P. Speis, Chief Advanced Reactor Branch Division of Project Management U.S. Nuclear Regulatory Commission Washington, C.C.

20555 Docket No. 50-267

Subject:

Fire Protection /ACM

Reference:

PSC Letter P-75024, December 15, 1975 Gentlemen:

This letter is to inform you that PSC has completed installation of the third phase of our pemanent improved fire detection and fire protection system and the permanent Alternate Cooling Method (ACM) as committed in our P-75024 letter, Walker to Denise, dated Decemoer 15, 1975.

These items were previously committed as restrictions to the rise-to-pcwer program following the first refueling.

Having satisfied our commitments, Fort St. Vrain is currently proceeding with our rise-to-power program.

If you have any questions, please contact me.

Very truly yours,

W C

f,psl,n [

N GM \\

Frederic E. Swart Nuclear Project Manager FES/FWT:ler Oo6V