POWER AUTHORITY OF THE STATE OF NEW YORK 10 COLUMBUS CIRCLE NEW YORK N. Y.10019 (212) 397.6200 GEORGE T BERRY EX ECUTIVE DIRECTOR FREDERICK R. CLARK C"
LEWIS R. BENNETT
- l.'"ul*t";n^:=
oEORoEL.i~oALLS
[
DIRECTOR VICE CHAIRml AN RICH ARD M. FLYNN JOSpH SC H M IEDER g
ROBERT 3. MILLONZ1 JOHN W. BOSTON February 8, 1979 "L' c' " R.,,,,,
witunu r.LuDDY JPN-79-9 Tsou,8 7. ucco,ss,,,,
CONTROLLER Director of Nuclear Reactor Regulation U.
S. Nuclear Regulatory Commission Washington, D.
C.
20555 Attention:
Mr. Thomas A.
Ippolito, Chief Operating Reactor Branch No. 3 Division of Operating Reactors
Subject:
James A. FitzPatrick Nuclear Power Plant Docket No. 50-333
Dear Sir:
By letter dated November 15, 1978, Mr.
B.
Grimes, Assistant Director for Engineering and Projects, requested that the Power Authority submit a license amendment application to incorporate the requirements of 10 CFR Part 50, Appendix I into the FitzPatrick facility Technical Specifications within 90 days (i.e., February 15, 1979).
The Power Authority finds that it requires additional time to complete its response.
We now plan to respond by April 16, 1979.
Very tru
- yours,
,/
/
/.
..w Pail]/ J.
Ear Assistant C ief Engineer-Projects 790214oM i 90
\\