Forwards Response to IE Bulletin 79-02,Revision 2 Re Pipe Support Base Plates.No Seismic Category I Supports Use Expansion Anchors Attached to Concrete Blocks
ML19260D656
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 01/11/1980
From: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
IEB-79-02, IEB-79-2, NUDOCS 8002110549
Download: ML19260D656 (2)


Text

-

TlG e TELEPHONE. (216) 622 9f100 m tLLUMIN ATING BLOG e $$ PUBLIC 50U A AE P o Box 5000 e CLEVELAND OHlo 44101 Dalwyn R. Davidson v:CE WESIDE NT siSTip ENGINE E R!NG AND CONST AUCTION January ll, 1950 Mr. James G. Keppler, Director Regicn III Office of Inspection and Enforcement U. S. Nuclear r. gulatory Concission Glen Ellyn, IL 63137 RE: Perry Nuclear Power Plant Docket Nes. 50 hkO; 50 LL1 IE Bulletin No. 79-02, Rev. 2 Dea: r.

Keppler:

In acccrdance with your reauest in Revision 2, the enclosed attachment has 'ec er prepared as an additional response to tne above Inspection and Enforcement bulletin. Our response was prepared in cond nction with our Architect / Engineer, Gilbert Associates, Inc.

Very truly yours, g ., .) T . > 6 --

9. 7) . 7. ,, ..

Dalwyn R. Davidson Vice President System Engineering and Construction DRD/cew Enclosure cc: Victor Stello, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Co==icsion Washington, DC 20555 1940 229 SN02110 yp

i PERRY L"JCLEAR PORER PLANT 4

Docket Nos. 50-440; 50-441 January 11, 1980 IE Bulletin No. 79-02. Rev. 2 The following responses correspond to their respective item numbers.

Response 2. The original Bulletin safety factors were applied for the maximum earthquake (SSE). Therefore, this aspect of Revision 2 has no effect on Perry.

Response 4. The x _;inal Bulletin response included a detailed explanation of the effects of preload on anchor bolt ultimate capacity under dynamic loading. Therefore, this aspect of Revision 2 has no effect on Perry.

Response 5 To date no seismic category I supports use expansion anchors attaching to concrete blocks. If any are used in the future, the requirements of this item will be addressed fully.

Response 6. Structural steel shapes when used with concrete expansion anchors were included in the original Bulletin response. Therefore, this aspect of Revision 2 has no effect on Perry.

Rerponse 7. This is not applicable to Perry.

Response 8. The requirement for " maintaining documentation of any sampling inspection of anchor bolts required by item 4 on site and available for NRC inspection" was formerly in item 4 of the original Bulletin and therefore needs no response. The remainder of the item affects holders of operating licenses only. Therefore this aspect of Revision 2 has no affect on Perry.

Response 9 Since the revised portions of itens 2 and 4 do not require additional response (see responses for these items above) no response for this item is necessary.

1943 230