Confirms 791228 Telcon W/Nrc Re Significant Nonconformances Identified During Data Analysis in Response to IE Bulletin 79-14.Followup Rept Will Be Submitted by 800110
ML19260C528
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 12/31/1979
From: Shaller D
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
REF-SSINS-6820 IEB-79-14, NUDOCS 8001070347
Download: ML19260C528 (1)


Text

.

DSCo X,,,

IN0/ANA & MICHIGAN ELECTRIC COMPANY DONALD C. COOK NLCLEAR PLANT P.O. Box 458, Bridgman Michigan 49106 (616) 465-5101 December 31, 1979 Mr. J.G. Keppler, Regional Director Office of Inspection and Enforcement United States Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 Operating License DPR-74 Docket No. 50-316

Dear Mr. Keppler:

This is to confirm our telephone report to your Mr. D. Boyd, Chief of Reactor ProjectsSection III, at 1615 hours0.0187 days <br />0.449 hours <br />0.00267 weeks <br />6.145075e-4 months <br /> on December 28, 1979.

At that time I informed Mr. Boyd that during analysis of the Unit 2 data gathered in response to IE Bulletin 79-14 four (4) significant non-conform-ances were identified relative to subject bulletin by our New York office.

A brief summary for each of these problems was also read to Mr. Boyd at this time.

A followup report will be submitted by January 10, 1980, as required by Technical Specification Section 6.9.1.8.

Sincerely, D.V, Shaller Flant Manager

/jas cc:

J.E. Dolan G. Olson R.S. Hunter J.M. Hennigan Y

O R.W. Jurgensen PNSRC 9 (\\

R.F. Kroeger J.F. Stietzel

\\

R.W. Kilburn E.L. Townley R.d. Masse, R0:III Dir., IE (40 copies)

R.C. Callen, MPSC Dir., MIPC (4 copies)

G. Charnoff, Esq.

)hhk 2b)e 3 AM 2 M9 S