Forwards Revised Final Deficiency Rept Re Potential Excessive Water Hammer Forces in Main Feedwater Sys
ML19259D373
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 10/10/1979
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19259D374 List:
References
NCR-MEB-79-1, NUDOCS 7910180387
Download: ML19259D373 (1)


Text

TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 37401 400 Chestnut Street Tower II October 10, 1979 Mr. James P. O'Reilly, Director Office of Inspe tion and Enforcement U.S. Nuclear Reg lacory Commission Region II - Suite 3100 101 harietta Stree Atlanta, Georgia 3 303

Dear Mr. O'Reilly:

SEQUOYAh NUCLEAR PLANT UNITS 1 AND 2 - POTENTIAL EXCESSIVE WATER HAMMER FORCES IN THE MAIN FEEDWATER SYSTEM - NCR MEB 79 REVISED FINAL REPORT The subject deficiency was initially reported to NRC-0IE Inspector C. R. McFarland on January 15, 1979. Interim reports were submitted on February 14, 1979, and March 13, 1979. A final report was sub-mitted on May 16, 1979. Enclosed is our revised final report.

If you have any questions concerning this matter, please get in touch with D. L. Lambert at FTS 854-2581.

Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nuclear Regulation and Safety Enclosure cc: Mr.Victorbeello,Jr., Director (Enclosure)[