Second Interim Rept of Deficiency Re Improper Anchor Bolt Matl.Final Rept Will Not Submitted Until 790815,due to Complexity of Identifying & Testing Suspect Bolts
ML19259C161
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 06/05/1979
From: Eric Turner
HOUSTON LIGHTING & POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
ST-HL-AE-349, NUDOCS 7906120430
Download: ML19259C161 (2)


Text

-

.y.

w l Houston r

company .

~

Electnc Tower '

l RO Box 1700 Houston. Texas 77001 June 5, 1979 SFN: V-0540 ST-HL-AE-349 Cirector, Region IV Office of Inspection and Enforcement 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76102

Dear Sir:

South Texas Project Units 1 & 2 Docket Nos. STN 50-498, STN 50-499 Second Interim Report on the Reportable Deficiency Concernino Improper Anchor Bolt Material On March 8,1979, pursuant to 10 CFR 50.55(e), Houston Lighting and Power Company provided your office with an interim report concern-ing the fabrication of anchor bolts from improper material. The letter indicated that a final report would be submitted by June 1,1979.

Prior to this, your office was informally notified by HL&P Quality Assurance of other potentially reportable defects in 1100 field fabricated anchor bolts. Since this notification was informal, and an explicit safety hazard could not be identified, it was deternined that a 30 day report as required by 10 CFR 50.55(e)(3) would not be necessary.

As a result of a technical evaluation, it was determined that the two problems identified above were related. Consequently, the two were merged as a common generic problem. HL&P had planned to have a final report available for your review on June 1,1979 as originally indicated. However, due to the complexity of completely identifying and thoroughly testing all suspect anchor bolts, it is now evident that the necessary information will not be available until August,1979.

2285 080 9 1 7906120//ID '

Houston Ughung & lbwer Company ST-HL-AE-349 Page 2 A final report will be submitted to your office by August 15, Ver truly yours, l .J / G C.T u E. A. Turner

Vice President Power Plant Construction

& Technical Services LRJ:bf cc: Director, NRC Office of Inspection & Enforcement /