Forwards Insp Rept 70-1201/78-15 on 78113-17.No Noncompliance Noted
ML19259A905
Person / Time
Site: 07001201
Issue date: 12/04/1978
From: Sutherland J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Silk E
BABCOCK & WILCOX CO.
Shared Package
ML19259A906 List:
References
NUDOCS 7901110184
Download: ML19259A905 (2)


Text

.

JERA "h

k* "8 0 UNITED sT ATEs jf 0g[o NUCLEAR REGULATORY COMMISSION R EGloN 11

.?

o

,3.

101 M ARIETTA STREET.N.W.

t

' 8 ATLANT A, GE oRGI A 30303 o

%*****/

DEC 0 4197B In Reply Refer To:

RII:JHD 70-1201/78-15 Babcock and Wilcox Company ATTN:

Mr. Edmond J. Silk, Plant Manager Nuclear Materials Division Commercial Nuclear Fuel Plant Post Office Box 1260 Lynchburg, Virginia 24505 Gentlemen:

This refers to the inspection conducted by Mr. J. H. Davis of this office on November 13-17, 1978 of activities authorized by NRC License No. SNM-1168 for the Commercial Nuclear Fuel Plant facility, and to the discussion of our findings held with Mr. J. Ficor at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the enclosed inspection report. Within these areas, the inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspectors.

Within the scope of this inspection, no items of noncompliance were disclosed.

We have examined actions you have taken with regard to previously reported unresolved items. The status of these items is discussed in the enclosed report.

In accordance with Section 2.790 of the NRC's " Rules of Practice",

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.

If this report contains any information that you (or your contractor) believe to be proprietary, it is necessary that you make a written application within 20 days to this office to withhold such information from public disclosure. Any such application must include a full statement of the reasons on the basis of which it is claimed that the information is proprietary, and should be prepared so that proprietary information identified in the application is contained in a separate part of the document.

If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Room.

7901110/ff

DEC 0 41978 Babcock and Wilcox Company Should you have any questions concerning this letter, we will be glad to discuss them with you.

Sincerely,

[J.T.Sutherland, Chief Fuel Facility and Materials Safety Branch

Enclosure:

Inspection Report No. 70-1201/78-15