POWER AUTHORITY OF THE STATE OF NEW YORK t o COLUMBUS CIRCLE NEW YORK, N. Y.10019 (212) 397-6200 GENERAL M NAGER FREoERICK R. CLARK AND CHIEF ENGINEER As' sis ANT G NERAL GEORGE L. ING ALLS MANAGER-GENERAL ViCE CHAIRM AN COUNSEL RICH ARo M. FLYNN WILBuR GRONDE ROBERT I MILLONZl JOHN W. BOSTON wiLuxu r. Luoor January 3, 1979

%"w'E l ",fR ATiONs IPO-182 rNOuxS r. uCCR ANN, ;R.

CO NTR OLL E R Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Attention:

Mr. A.

Schwencer, Chief Operating Reactors Branch - 1

Subject:

Containment Purging During Normal Plant Operation Indian Point #3 Nuclear Power Plant Docket No. 50-286

Dear Mr. Schwencer:

The data requested in your letter of November 28, 1978 necessitates an extensive investigation which cannot be completed by the January 5, 1979 submittal date.

Work on this matter is continuing and we now plan to be able to respond by February 26, 1979.

Very truly_yours_,

) f' JJ Earlf Pau J.

Ass 6. Chief Engineer-Projects Y

7901100M 0

\\

f