ML19259A576

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-483/78-10 on 781002-04.Noncompliance Noted: Failure to Follow Procedures for Weld Control & for Timely Response to Audit Findings
ML19259A576
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/20/1978
From: Hayes D, Naidu K, Schweibinz E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19259A572 List:
References
50-483-78-10, NUDOCS 7901080076
Download: ML19259A576 (17)


See also: IR 05000483/1978010

Text

' . '

~

.

'

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-483/78-10

Docket No. 50-483

License No. CPPR-139

Licensee: Union Electric Company

P. O. Box 149

St. Louis, MO 63166

Facility Name:

Callaway, Unit 1

Inspection At:

Callaway site, Callaway County, MO

Inspection Conducted:

October 2-4, 1978

[, S. h5w&E

Inspectors:

E. R nSchweibinz

//-/7~28

\\ j,

N

g j

3 c )$'

K. R. Na\\ td

,

idu

E. O.

[+<- J. C. Mattia (Regi6n I)

// ~/ 2 ~ N

r. r. 4L

h C. R. Oberg %(Region IV)

/ ', ~ / , ~ ,8

Approved By:, D. W.

ay s

er

//

Oj!M

Projects Section

/

,

Inspection Summary

Inspection on October 2-4, 1978 (Report No. 50-483/78-10)

_

Areas Inspected:

Reactor Pressure Vessel movement act ivities; Site tour;

Cable Tray support installation; Cable Tray support welding activities;

Cable Tray support welding records; Containment structural steel welding

records; Safety-related structures; Reactor building interior concrete

structures; Licensee site audits; and safety-related components. The

inspection involved a total of 78 inspector hours on site by four NRC

inspectors.

Results: Of the ten areas inspected no items of noncompliance or

deviations were found in eight areas; two apparent items of noncompliance

were identified in two areas (infraction - failure to follow procedures

for weld rod control - Section I, paragraph 2; infraction - failure to

follow procedures for timely response to audit findings - Section III).

7soiwso76

.

.

.

DETAILS

Persons Contacted

Union Electric Company (UE)

  • W.

H. Weber, Manager, Nuclear Construction

  • R. L. Powers, Site Quality Assurance Group Leader
  • W.

H. "'nhl, Ouality Assurance Engineer

  • S. M. Ho,an, Quality Assurance Assistant Engineer

M. I. Do i.e, General Superintendent, Callaway Construction

J. R. Vcatch, Quality Assurance Assistant Engineer

J. V. Laux, Quality Assurance Assistant Engineer

J. C. Gearhart, Quality Assurance Assistant Engineer

J. Baker, Construction Supervisor

Daniel International Company (Daniel)

  • H.

J. Starr, Project Manager

  • E.

D. McFarland, Construction Engineering Manager

  • W.

C. Westhoff, Quality Control Manager

  • J. A. Holland, Project Quality Assurance Manager
  • W.

L. Sykora, Assistant Project Manager

  • J.

N. Kaelin, Project Audit Response Coordinator

S. R. Farwell, Rigging Consultant

The inspectors also contacted and interviewed other licensee and contractor

personnel, including Craf tsmen, QA/QC, Technical and Engineering staff

members.

  • denotes those attending the exit meeting.

,

Licensee Action on Previous Inspection Findings

(Closed) Unresolved item (50-483/78-01-08, 50-483/78-03); The QA/QC system

implemented by the licensee does not require that nonconforming items

in storage be tagged or otherwise identified relative to their status.

Administrative Procedure number AP-IV-09, Revision 0, dated September 18,

1978, has been issued. This procedure requires that items found to be in

nonconformance of the storage requirements that have deteriorated or

.

are suspected to have deteriorated will have a nonconformance report

initiated against them.

It further requires that if equipment is found

to be in adverse storage conditions but not nonconforming, a notation

will be made on the preventive maintenance work order, and a copy placed

,

in a pending file. The pending rile will be reviewed weekly to insure

~

that correttive action is taken to resolve the discrepancy. This item

is closed.

-2-

.

.

(0 pen) Unresolved (50-483/78-06-01)'

QA Engineering procedure QE-301

did not address what is to be done with comments generated from

reviewing documents received from o ganizations. The licensee stated

that their QA procedure, QE-303 is the procedure for disposition of

comments and they will revise QE-301 to reference QE-303.

This item

remains open.

(Closed) Noncompliance (50-483/78-06-02):

Failure to provide objective

evidence that Alpha Portland Cement Company's QC program (Revisions 1,

2 and 4) were reviewed and approved. The inspector reviewed documenta-

tion dated August 24 and September 15, 1978, indicating that the

Alpha Portland Cement Company's QC program (Revisions 1, 2 and 4) had

been reviewed and approved. In addition to this program the licensee's

constructor performed a 100% audit of all their safety related purchase

orders to verify that all QA programs have been reviewed and approved.

The Daniel International letter dated September 13, 1978, stated that

this 100% audit had been completed and all QA programs have been ~eviewed

and approved. This item is closed.

(Closed) Noncompliance (50-483/78-06-03):

Failure to provide objective

evidence that Pittsburgh Testing Laboratory's QC procedures No. A-SL

(Revision 2) and No. S l (Revision 2) had been reviewed and approved.

The inspector reviewed licensee's documents dated August 22, ar.d

October 4, 1978, indicating that the above Pittsburgh Testing

Laboratory procedures had been reviewed and approved.

This item is

closed.

(Closed) Noncompliance (50-483/ 8-06-04):

The licensee's QA proccdure

f ailed to provide several of the requirements in ANSI N45.2.11 for

design external interface control. The licensee issued a QA procedure

No. QE-3.8 Revision 0, dated September 15, 1978, which addressed

design-external interface control. The inspector reviewed this

document and found it to meet requirements.

This item is closed.

.

(Closed) Noncompliance (50-483/78-06-05):

Engineering Change Notices

(ECN) issued by the site A/E are now approved by the licensee in

accordance with QE-319, Review of Engineering Change Notices prepared

by the Site Architect Engineer, Revision 0 (9/15/78).

This item

is closed.

(Closed) Noncompliance (50-483/78-06-06): QE-303 Review of Design

Documents, Revision 7 (9/15/78) now defines the requirements for

document review and comment.

Internal procedures for Bechtel and

SNUPPS Staff Procedures are in agreement with QE-303.

This item is

closed.

-3-

.

(Closed) Noncompliance (50-483/78-06-09): QE-303, paragraph 2.0,

Scope, has been changed to define responsibility for review. See Item

50-453/78-06-06 above . This item is closed.

(Closed) Unresolved (50-483/70-06-08):

This item is closed based on the

clarification of review requirements in QE-303.

(Open) Noncompliance (50-483/78-06-10):

This item remains open pending

a change to QE-314, paragraph 5.2, for an appropriate reference to QE-301.

(0 pen) Noncompliance (50-483/78-07-07 and 50-483/78-07-08):

Changes to

AP-IV-04 and AP-IV-05 are still in the review stage and have not been

issued. The licensee representative stated that the changes will be

issued by October 31, 1978. This item remains cpen.

(Open) Unresolved (50-483/78-06-07):

This item refers to adequacy of

distrubution and filing control system. After discussion with the licensee

representative it was determined that this item vill need to be reviewed

further during a future inspection.

The licensee will also review this

matter internally. The IE inspector determined that the review of

safety-related items by personnel outside of the Q,A program was satisfied

by a change to paragraph 5.1.3 of QEC-303, which rer

es final

evaluation to be done by Nuclear Engineering. Thi, item remains open.

(open) Unresolved item (50-483/78-07-04):

Resurvey of the safety-related

columns in the Auxilary Building. Some columns in the Auxilary Building

were determined to be out of plum during a resurvey. The contractor

provided some additional information to the inspector during the current

inspection however, this item remains open pending further review.

(0 pen) Unresolved item (50-483/78-07-05):

Inadequate provisions to control

welding process.

It was previously reported that the contractor agreed to

develop suitable provisions to establish that welding is performed within

the parameters specified in the Welding Procedures specification.

The con-

tractor has developed an interim instruction, Welding Equipment Voltage

-

Surveillance, Procedure number 11-030, dated October 4, 1978.

This item

remains open pending review of the implementation of this procedure.

(Closed) Followup Item (50-483/78-02-05): Welding procedure implemen-

tation for cable tray supports. This item is addressed in Section II,

paragraphs 1, 2, and 3 of this report. This item is closed.

Functional or Progran Areas Inspected

Details of Functional or Prog am areas inspected are documented in Sections

1, 2, 3, and 4 as follow..

.

-4-

.

Section I

Prepared ty E. R. Schweibinz

Reviewed '2y D. W. Hayes, Chief

Reactor Projects 4ection

1.

Reactor Pressure Vessel and Upper Internals Removal from a Barge,

Hauling and Placing in Storage - Review of Implementing Procedures

The following procedures were received from the licensee for Region

III office review on September 14, 1978.

Procedure

Revision

Approval

Number ___

Number

Date

Description

101

2

---

Unloading a Reactor

Vessel from a berge, haul-

ing and placing in storage.

103

1

9/11/78

Cantilever gantry

crane.

105

1

Unloading the upper

---

internals from a barge,

hauling and placing

in storage.

106

1

Unloading the Reactor

---

head from a barge, hauling

and placing in storage.

107

2

---

Load test of haul road

and transport trailer.

,

108

0

---

420 ton load test.

Procedur- specification numbers 1, 2, 3, 4, and 5 all Revision 0

approved on September 5, 1978, titled Prequalified Joint Welding

Procedure were also supplied for review.

The RIII review of the above procedures was completed on September 15,

1978.

Comments regarding the above procedures were telep? ned to

the UE Qaulity Assurance Group Leader on the same day.

One of

the comments provided to Union Electric suggested that the results

of inspections performed at the site should be available to the

-5-

licensee, this was not clear as written in the Procedures.

The

Procedures were revised an' addendum I was added to include a statement

that "All inspection documentation will be forwarded to Daniel Inter-

national Corporation for their review and Quality Assurance documentation."

The addition of the above sentence to the Procedures satisfied the RIII

concern. The following list of approved Procedures were provided to the

RIII inspector on October 3, 1978.

Procedure

Revision

Approval

Number

Number

Date

Description

101

2

9/21/78

Unloading a Reactor Pressure

Vessel from a barge, hauling

and placing in storage. With

Addendum 1 and 2.

103

1

9/11/78

Cantilever gantry crane. With

Addendum 1, dated September 27,

1978.

105

2

9/15/78

Unloading the upper internals

from a barge, hauling and

placing in storage. With

Addendum 1.

106

1

9/21/78

Unioading the reactor head

from a barge, hauling and

placing in storage. With

Addendum 1 and 2.

107

2

9/15/78

Load test of haul road and

transport trailer.

108

1

9/15/78

420 ton load test.

With

Addendum 1.

.

109

0

9/26/78

Upending the upper internals,

removing them from shipping

stand and setting them in

storage. With Addendum 1.

110

0

9/19/78

Mobile crane test.

With

Addendum 1.

The above Procedures were reviewed and appeared to be consistent with

requirements.

During this inspection the RIII inspector did witness part of the load

test of the haul road and the transport trailer.

-6-

..

.

.

.

.

The 420 ton load test occurred on September 25, 1978, when 859,986 pounds

were lif ted, which is approximately 430 tons.

430 tons is approximately

115% greater than the heaviest lif t that will be made which is the lif t

of the Steam Generators which weigh approximately 373.4 tons including

all of their rigging. The Reactor Pressure Vessel (RFV) and its

associsted rigging weigh approximately 356 tons.

The Reactor Pressure

Vessel was lifted from the barge and placed on the transporter on

October 9, 1978. The RPV was then transported from the barge area to

the storage area on October 10, 1978.

No items of noncompliance or deviations were identified.

(483/78-10-01)

2.

Site Tour

During the site tour the following item we; identified.

A large quantity

of E7018 weld rod stubs were found in the stiffener channels that are

attached to the liner plate ir the area of the 14th lift of the contain-

r rt exterior wall. Weld rod stubs should be put in stub containers

and not left in the area where the welding is occurring, which would

leave the possibility that they could be reused.

Paragraph number 3.16 of Work Procedure number WP-503, Control of

welding consumables, dated May 5, 1978, Revision 6 states in part

" Loose electrodes and filler wire shall not be lef t lying around but

shall be contained in a portable container or a weld pouch."

Inner

office memo CM-450 dated June 9, 1977, from the Welding Superintendent

to All Superintendents and Welders on the subject of Rules for

Welding Control states in part " Weld rod stubs shall be put in stub

cont iners and emptied in a trash container at the end of the st'ft."

This is an item of noncompliance with 10 CFR 50, Appendix B,

Criterion V.

(483/78-10-02)

.

-7-

.

.

Section II

Prepared by K. R. Naidu

Reviewed by R. L. Spessard, Chief

Engineering Support Section 1

1.

Observation of Installation of Cable Tray Supports

The inspector observed work performance on partially completed work

and completed work on the cable tray supports identified as 4J1D20,

IU1B22 and 4JLA13-1 in the control room building at elevations

1984'-0", 2000'-0" and 2016'-0" respectively and determined that

work and inspection requirements were met in the following areas.

a.

Specified materials were used.

b.

Installation of the cable tray supports were in accordance

with Raceway Plan Control Room Building drawing - E-0R3211(Q),

E-0R3311(Q) and E-OR-3411(Q) for elevations 1984'-0", 2000'-0"

and 2016'-0" respectively.

c.

Qualified inspectors perfort'd the inspections.

d.

Records were legible and retrievable.

e.

Visual inspections were being performed.

No items of noncompliance or deviations were identified in the

<

above areas.

2.

Observation of Cable Tray Support Welding Activities

The inspector selected the following cable tray supports to ascertain

-

whether the attachment welds were in conformance with the relevant

drawings:

At Elevation 1984'-0"

Cable Tray Support

Drawing

Detail

4J1A 13-1

C-0401

9

4J1A 13-2

C-0401

11

C-0402

8

.

-8-

At Elevation 2000'-0"

Cable Tray Support

Drawing

Detail

IUlB22

C-0409

9

C-0401

10

IJ1C35A

C-0401

19

C-0402

8

IJ1C35B

C-0401

19

C-0402

8

At Elevation 2016'-0"

Cable Tray Support

Drawing

Detail

4J1D20

C-0401

12

C-0401

4

2J1A10

C-0405

10

C-0401

12

IJ1Dll

C-0401

4

C-0401

12

1J1D20

C-041s

3

The inspector determined that size and location of the welds

conformed to the drawings. The length of the weld on one side

was longer than specified by 2 inches. For example, drawing

C-0404(Q) titled " Typical Details Cable Tray Supports". Sheet

No. 4 in detail 16 requires a Unistrut type P1357 bracket to

be welded with a 3/16" size weld 1 1/2" long r.a three sides.

The dimensions of the bracket sides are 1 1/2" X 1 1/2" X 3 1/2".

-

The licensee agreed with the inspector that althe .rh the additional

reinforcement on one side is not detrimental, the we:d should con-

form to the drawing requirements. The licensee stated they had

verbally appraised the A/E of this apparent discrepancy but had not

received any clarification to date

The inspector informed the

licensee that this matter is con 4 ered an unresolved item until

the clarification provided by the A/E is reviewed and determined

acceptable.

(483/78-10-03).

No items of noncompliance or deviations were identified in the

above areas.

-9-

.

.

3.

Review of Cable Tray Supports Welding Quality Records

The inspector reviewed the Quality Records documenting the inspec-

tions on Cable Tray Supports welds listed in paragraph 2 and

determined that the applicable inspection requirements were met in

the following areas

a.

Weld Procedure Specifications (WPS) #N-1-1-A-12 dated June 10,

1978, Revision 1 and N-1-1-A-13 dated June 10, 1978, Revision

1, were used where applicable,

b.

Electrodes type E7018 were used.

c.

The welds were visually inspected by qualified inspectors to

AWS D1.1-75 requirements,

d.

Periodic checks of the current were made to determine that the

current was within the range specified in the WPS.

e.

Surveillances documented the serial number of the portable

weldrod even used to establish that only approved weldrod was

used to perform welding.

f.

Inspections were documented on Welding Surveillance reports

instead of separate welding inspection reports, as described in

t'.e procedure QCP 507. The licensee agreed to review this

matter in order to resolve this inconsistency.

The inspector

informed the licensee that this matter is considered an

unresolved item and that action taken will be reviewed during

a subsequent inspection (483/78-10-04).

No items of noncompliance or deviations were identified in the

above areas.

4.

Review of Containment Structural Steel Welding Records

-

The inspector observed welding activities relative to the installation

of Reactor Refuelling Canal (RRC) Liner plates. Discussions with the

licensee and DI personnel indicate that the installation of the

Stainless Steel Liner plates to the seismic Category 1 RRC concrete

structure was not considered 'Q'

listed, and thus safety related only in

those sections where the liner plate is attached to the seismic

Category 1 embedcent by welding. Horizontal and vertical seam

welds attaching liner plata to liner plate were not considered

safety related and were being performed by Alberici, a subcontractor

without a QA program. Further discussions with Alberici personnel

indicate that the liner plates are welded by automatic machines.

The final welds are subjected to Penetrant Examination by an

- 10 -

.

1

  • W

.

3

.

independent testing agency, namely Pittsburgh Testing Laboratories

(PTL). The inspector did not review the records generated by Alberici

since the work performed was not considered safety related by the

A/E. This matter is considered unresolved and is being forwarded to

IE:

Headquarters for resolution.

(483/78-10-05).

The inspector selected Field Welds (FW) #1, 2, 3 and 4, identified

on drawings C-0L-2922(Q) Revision 7 and C-OL-2931, and reviewed the

relevant documentation.

These welds attach liner plate cut-out

sections, to which embeds identified as 64PSA and 64PSB were welded,

to the liner plates installed in the RRC.

The inspector determined

that the records reflect work accomplishment consistent with applicable

requirements in the following areas:

a.

Inspections were documented in the Weld Control Record.

b.

Preheat temperature was specified as 60 F and was verified.

c.

Fit up was checked.

d.

Weldrod withdrawal was identified.

e.

Welding Procedure #N-8-8-A6 was specified,

f.

Weldors were identified; qualification records indicate that

they were qualified.

g.

Visual inspections were performed on the completed welds,

h.

The welds were subjected to Liquid Penetrant (PT) examination.

Records indicate that the welds FW2, FW6, FW4 were examined

according to DI Magnetic Particle procedure 7.3C Revision 1,

utilizing dye penetrant type SKL-5, developer type SKD-5 and

cleaner type SKC-5 all manuf actured by Magnaflux.

The dwell

,

time was ten minutes, drying time was five minutes, and developing

time was seven minutes. The weld was sprayed and wiped clean.

No unacceptable indications were identified.

1.

Records of the Level II NDE inspectors indicate that they are

qualified.

j.

Records were legible end retrievable.

No items of noncompliance ce deviations were identified in the above

areas.

.

- 11 -

.

.

.

5.

Observation of Safety Related Structures Work Activities

The inspector observed steel columns 3C2AD and SC4AD, identified

on A:oerican Bridge drawing #K6726E2, in the Emergency Diesel

Generator Building. The columns had been erected, and during a survey,

it was determined that the base plates of the column was 3/8" lower

than specified in the drawing. Corrective action recommended

and approved was to raise the base plate 3/8" by placing grout

underneath it.

The inspector determined that inspection require-

ments were met in the following areas:

a.

Material Control Report (MRC) 02574 identifies that the material

was received without shipping damage.

Bechtel C 321-D Form

indicates that the necessary shop inspections were performed.

b.

Installation was to Bechtel drawing #COS 5211 Revision 1.

c.

Specified materials were used.

d.

Inspections of the instellation were documented in Structural

Steel report dated July 20, 1978.

The inspector observed that the splices between columns 727C7J1A and

614C7J1A and 702C6JA and 601C6JA had been identified with a noncon-

formance report (NCR) tag 2-3772-C-A.

The columns are installed in

the auxiliary building at elevation 2002'0".

Review of NCR 2-3772-C-A

dated September 6, 1978, indicates that the columns do not have

bearing contact on milled surfaces at the splice connection due to

misfabrication.

Corrective action recommended was to enlarge the bolt holes on columns

727C7J1A by 3/32" and column 702C6JA by 1/8" utilizing a magnetic drill.

Corrective action had not been completed.

The NCR was legible and

retrievable. The inspector has no further questions on this matter

at this time.

'

No items of noncompliance or deviations were identified in the above

areas.

6.

Observation of Reactor Building Interior Concrete Structures

The inspector observed several areas on the Reactor Building interior

walls which exhibited inadequate consolidation. The licensee informed

the inspector that NCR 2-3950-C-A documents these areas as non-

conforming. The NCR identifies voids in pour Nos. 2C231W32, 2C231W24,

2C231W27, 2C231W34, 2C231W31 and 2C231W35. Corrective action

recommended to repair the voids appeared to be adequate.

Supervision

was informed of the contents of the NCR to prevent recurrence. The

- 12 -

'

. .

.

.

.

'

.

>

.

inspector stated that it was not clear whether the supervision in

turn passed the coments to the craf t personnel who use the vibrators.

The DI personnel stated that when the trend persists they indoctrinate

the craft personnel and agreed to document in the NCR the instances

when training sessions were held. The inspector has no further

questions on this matter at this time.

No items of noncompliance or deviations were identified in the above

areas.

.

.

- 13 -

.

-

+

.

Section III

Prepared by J. C. Mattia (Region I)

Reviewed by R. W. McCaughy (Region I)

Licensee Site Audits

The inspector reviewed various licensee's audits of the site constructor

to verify the following:

Audits were scheduled and conducted.

-

Scope of Audits were consistent with the purpose stated.

-

-

Appropriate standards were referenced for measuring performance.

-

Audited organizations received copies of audit reports.

-

Audited organizations provided timely response to audit findings.

Appropriate corrective action was taken and timely followup

-

action, including re-audit of deficient areas.

The licensee's audit schedule and the following audit files, which included

audit reports, checklists, audit plans, action letters, response letters,

response evaluation letters, pre and post audit conference documents for

a specific audit were reviewed:

Audit Date

Type of Audit

.

June 22-28, 1977

Material, Receiving, Storage and

Processing

April 20-20, 1977

Material Processing Facility

  • May 12-13, 1977

Field Engineering (Survey)

  • September 7-13, 197~

Records Management System

'

  • April 13, 1977

Civil Laboratory

  • June 19-23, 1978

Appendix B Critaria II, XVI,

c.nd XVII

  • July 17-21, 1978

Appendix B Criteria IV, VIII,

XIII and XV

September 11-12, 1978

Subcontractor for Reactor

Pressure Vessel Lift

The inspector did determine from his review of the above eight audits and

associated dccuments that the licensee was complying with the audit require-

.

ments, except in one area. For five of the eight audits reviewed the

- 14 -

_

.

.

.

inspector determined that the constructor (Audited Organization) did

not respond within the required time.

The IE inspector pointed out that

ANSI N45.2.12 paragraph 4.5.1 requires that the Audited Organization review

and investigate adverse audit findings and respond to the audit report

within thirty days after receipt, giving results of the review and investi-

gation. Also, UE QA Procedure QA-106 Revision 5, paragraph 5.3.4 requires

that responses to audits, where corrective action is indicated are to be

submitted within thirty days after receipt of the audit report.

The

audits denoted above with an asterick are the audits that have exceeded

the thirty day requirement by ten to thirty-four days.

This item is considered an item of noncompliance with 10 CFR 50,

Appendix B, Criteria V (483/78-10-06).

.

- 15 -

.

,

. .

-

Section IV

Prepared by C. R. Oberg (Region IV)

Reviewed by W. A. Crossman (Region IV)

Safety Related Components - Review of Quality Assurance Implementing Procedures

The IE inspector reviewed the procedures listed below as they pertain to

safety related components and their inspection, installation, and maintenance.

The following procedures were reviewed:

AP-IV-01

Material Control Functions, Revision 3 (August 9,1978)

AP-IV-09

Storage and Maintenance, Revision 0 (September 18, 1978)

AP-VII-07

Material and Equipment Receiving and Inspection,

Revision 1

(December 5, 1977)

AP-VII-09

Material and Equipment Storage and Handling, Revision 1,

(January 11, 1978)

AP-IX-05

Material Storage and Control, Revision 5 (March 24, 1978)

WP-114

Rigging, Revision 3 (June 6, 1978)

WP-210

Installation of Mechanical Equipment

QCP-210

Inspection of Installation of yechanicalEquipment,

Revision 2 (October 10, 1978)

WP-305

Installation of Electrical Equipment, Revision 1

(June 26, 1978)

QCP-ll4

Inspection of Material / Equipment Rigging and Handling,

Revision 0 (July 25,1977)

QCP-305

Inspection of Electrical Equipment Installation,

Revision 1 (July 14,1978)

Interim Changes:

AP-VII-09

ICP-1

Revision 0

September 18, 1978

AP-IX-05

ICP-1

Revision 0

September 18, 1978

AP-IV-09

ICP-1

Revision 0

September 29, 1978

-

AP-IV-09

ICP-2

Revision 0

October 3, 1978

AP-IV-01

ICP-1

Revision 0

September 18, 1978

-

The inspector determined that the requirements of ASNI N45.2.2 - 1972, and

the referenced standards therein, have been included in the above procedures.

Specifically,

1.

Receipt inspections determine that components are undamaged, are in

conformance with purchase specifications, and are properly identified.

Receipt inspection reports are required.

1/ Issued October 2, 1978.

- 16 -

.

..

.

-

d

.-

,

t

.

.

2.

Installation, testing and inspection activities are in accordance

with specifications and are to be done in accordance with written

procedures. Storage levels are determined in accordance with speci-

fication and procedure requirements.

3,

Handling equipment and crane lifting requirements have been established

and appropriate tests are required prior to special lifts.

4.

Post installation (storage in place) inspect *on and preservation

requirements are established prior to need and are adequately controlled

by procedures.

No items of noncompliance or deviations were identified.

Unresolved Items

Unresolved items are matters about which more information is required

in order to ascertain whether they are acceptable items, items of

noncompliance, or deviations. Unresolved items disclosed during the

inspection are discussed in Section II, paragraphs 2, 3 and 4 of the

Details Section of this report.

Exit Meeting

.

The inspectors met with site staff representatives (denoted in the

Persons Contacted paragraph) at the conclusion of the inspection on

October 4, 1978. The inspectors summarized the scope and findings of

the inspection, including the two apparent items of noncompliance

identified in Section I, paragraph 2 and Section III of the Details

Section of this report.

.

e

9

f

-

.

b

'

.

.

- 17 -

. . . .

.

_

h