Summary of 791204-05 Site Visit by NRC Forecast Panel Re Const Status & Preoperational Test Program.Panel Concluded Const Is Approx 50% Complete
ML19257D590
Person / Time
Site: Clinton Constellation icon.png
Issue date: 01/21/1980
From: Buckley B
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
NUDOCS 8002050093
Download: ML19257D590 (6)


Text

.

_pa "'Cw 0,

UNITED STATES

+

[ i '

my i NUCLEAR REGULATORY COMMISSION s%' 7/

f WASHINGTON, D. C. 20555 7,

%.."../ !

./

JAN 211980 Docket No. 50-461 FACILITY:

Clinton Nuclear Power Station, Unit 1

SUBJECT:

SUMMARY

OF DECEMBER 4-5, 1979 FORECAST PANEL SITE VISIT TO CLINTON NUCLEAR POWER STATION, UNIT 1 BACKGROUND:

The NRC Forecast Panel (B. Buckley, W. Lovelace, H. Wescott) made a site visit to the Clinton Nuclear Power Station at the request of the Illinois Power Company to review the progress made in the status of construction for fuel loading since our June 1979 visit.

A list of meeting attendees is enclosed (Enclosure 1).

At the Forecast Panel's site visit in June 1979 the applicant stated that construction was 47.6% complete and that their projected fuel load date was April 1,1982; the Forecast Panel stated that, in their view, construction was 32% complete and estimated a nominal construction completion date of June 1983.

On the afternoon of December 4,1979 we met with the applicant ind their general contractors Baldwin Associates and Sargent and Lundy and discur, sed the status of construction, the schedule for completion of construction, and the preopera-tional test program.

The apolicant described the bulk quantities installed to date and the total to be installed for several quantities of material as follows:

Total Estimated Quanti ty Percent Material Quanti ty Installed Comolete Concrete cu. yds.

296,800 259,301 I

87.4 Lg. Pipe (Total lin. ft.

316,000 152,650 48.3 Lg. Pipe Bldg.

lin. ft.

194,500 58,950 30.3 Small Pipe 196,700 18,100 9.2 Cable Tray 92,500 29,998 32.4 Conduit (exposed 270,000 11,770 4.4 metal)

Wire and Cable 4,210,000 4,467 0

(power) f Terminations 240,000 175

'O 1872 017

/)

800203n 0 95

JAN 211930,

The applicant stated that they had reduced the 156 days negative float reported in June 1979 to 105 days and had installed the reactor pressure vessel in place on October 7,1979; a target date that had been set 18 months ago. They stated that the status of construction is 57.8% complete as of October 31, 1979 and that their estimated fuel load date is April 1,1982.

Following a tour of the site on December 5, the Forecast Panel stated, during the exit meeting, that good progress had been made since the June 1979 visit.

Nevertheless, based on the quantities of both materials remaining to be installed and a general com-parison of the remaining work to be completed at Clinton, Unit I with other projects at similar stages of construction, it was our view that the status of construction is approximately 46% complete with a nominal fuel load date of April 1983.

The applicant vigorously disagreed with our estimates and expressed strong confidence il their estimates.

Subsequent to the meeting Mr. Koch of Illinois power Compny informed the licensing project manager, on December 14, 1979, that the tatt estimated quantity of metal conduit (exposed and buried' was 481,000 linea

  • feet and that 202,000 linear feet had been installed.

I told Mr. Koch that I would discuss this with Mr. Lovelace upon his return on January 7,1980 and with Mr. H. Wescott.

Following the Forecast Panel's review of this new infomation, we concluded that the status of construction is approximately 50% complete and our estimated nominal fuel load date is March 1983. A list of attendees at the exit meeting is enclosed (Enclosure 2).

iD. (, p% c n

e icJ B. C. Buckley, Project Fanager Light Water Reactors Branch No. 1 Division of Project Management

Enclosures:

1.

Attendance List December 4, 1979 Meeting 2.

Attendance List December 5,1979 Meeting cc:

See next page 1872 018

Mr. L. J. Koch Mr. L. J. Koch, Vice President Illinois Power Company 500 South 27th Street Decatur, Illinois 62325 cc:

Mr. Peter V. Fazio, Jr.

Schiff, Hardin & Waite 7200 Sears Tower 233 South Wacker Drive Chicago, I'.linois 60606 Mr. George Wuller Licensing Coordinator Illinois Power Company 500 South 27th Street Decatur, Illinois 62525 e

1872 019

ENCLOSURE 1 LIST OF ATTENDEES AT DECEMBER 4, 1979 MEETING NRC Illinois Power Comoany Baldwin Associates B. C. Buckley G. Brashear W. Harrington W. Lovelace J. Greet:

R. Hyden H. Wescott J. Hampton R. Neeb

0. Holtecher J. Stewart V. Howard T. Plunkett J. Tonias G. Wuller Sargent & Lundy R. Heider 1872 020

ENCLOSURE 2 LIST OF ATTENDEES AT DECEMBER S,1979 MEETING NRC Illinois Power Comoany

,Baldwin Associates B. Bucklcy R. Blackburn B. Harrington W. Lovelace G. Brashear R. Hyden H. Wescott D. Holtzscher R. Neeb V. Howard J. Stewart J. Grier T. Yearick L. Koch T. Plunkett T. Tonias G. Wuller Sargent & Lundy R. Heider 1872 021