Discusses 790715,1030, & 1204 Ltrs Seeking Authorization to Increase Power Level.Response to NRC 791228 Question Still Outstanding.Ie Evaluation Is Needed by 800315 for Review
ML19257C929
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 01/15/1980
From: Gammill W
Office of Nuclear Reactor Regulation
To: Mosely N
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
NUDOCS 8001310091
Download: ML19257C929 (1)


Text

t a

f

'h g1putag[o UNITED STATES g

y

g NUCLEAR REGULATORY COMMISSION yi

E WASHINGTON, D. C. 20555 E

o l

%.V [

January 15, 1980 Docket No. 50-285 MEMORANDUM FOR:

N. C. Moseley, Director Division of Reactor Operations Inspection FROM:

William P. Gammill, Acting Assistant Director for Operating Reactor Projects Division of Operating Reactors

SUBJECT:

FORT CALHOUN, UNIT NO. 1, OMAHA PUBLIC POWER DISTRICT (0 PPD), STRETCH POWER REQUEST By letter dated July 15, 1979, as supplemented by letters dated October 30 and December 4, 1979, OPPD requested authorization to increase the power level at Fort Calhoun from 1420 MWT to 1500 MWT.

Responses to our questions to OPPD dated December 28, 1979, are still outstanding.

As part of our review, we are considering OPPD's past capability to safely operate Fort Calhoun, Unit No.1.

In this regard, we request that 0I&E evaluate the past management perfonnance of OPPD and provide a discussion of any outstanding inspection items that relate to stretch power operation.

We have determined that we would need the OI&E evaluation by March 15, 1980, to be consistant with our review schedule.

Please contact Mr. Peter Erickson at 492-7435 if you have any questions about this request.

b. k e.,,,.e William P.

ammill, Acting Assistant Director for Operating Reactor Projects Division of Operating Reactors cc:

D. Eisenhut L. Shao R. Vollmer J. R. Miller B. Grimes R. Reid T. J. Carter P. Erickson W. Russell R. Ingram 1843 261 p

69/

800131 0 4r