d I' Consumers O:"
D000r 1
Stephen H. Howell g
eg f
Senior Vice President
'/
General of fices: 1945 West Pernall Fload, Jackson, Michigan 49201 * (517) 788 4453 January 11, 1980 Hove-h-80 Mr J G Keppler, Regional Director Office of Inspection and Enforcement Region III US Huclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137 MIDLAND UUCLEAR PIJJIT UNIT N0 1, DOCKET Ho 50-329 UNIT NO 2, DOCKFr NO 50-330 NI/RPS GROUNDING CONCERN
Reference:
- 1) Letter, S H Howell to J G Keppler; Midland nuclear Plant; Unit No 1, Dceket No 50-329; Unit No 2, Docket No 50-330; NI/RPS Grounding Concern; Hove-h8-78; dated April 6,1978
- 2) Letter, S H Howell to J G Keppler; Midland Nuclear Plant; Unit No 1, Docket No 50-329; Unit no 2, Docket No 50-330; NI/RPS Grounding Concern; Hove-85-78; dated May 30, 1978
- 3) Letter, S H Howell to J G Keppler; Midland Huclear Plant; Unit No 1, Docket No 50-329; Unit no 2, Docket no 50-330; NI/RPS Grounding Concern; Hove-152-78; dated August 30, 1978 h) Letter, S H Howell to J G Keppler; Midland Huclear Plant; Unit No 1, Docket No 50-329; Unit no 2, Docket No 50-330; NI/RPS Grounding Concern; Hove-237-78; dated August 31, 1979 The referenced letters were interim reports. This letter is a final 50.55(e) report regarding the above subject.
CPCo vill institute the B&W periodic test program for the UI/RPS cabinets in order to provide assurance that the Ground connection has not been lost and to obtain baseline data.
As indicated in Reference h, the B&W test specification (No 62-1005067-00) was revised to include this test program. The detailed CPCo implementing procedures will be based on the E&W test specification.
Releare of these procedures has been rescheduled to be compatible with the overall Project schedule.
'Wp 6
WRB/1r i770 304 8001180
2 Hove 1 -80 4
CC: Director of Office of Inspection and Enforcement Att: Mr Victor Stello, USIIRC (15)