Motion to Clarify or Correct Special Prehearing Conference Order Re Completion of General Discovery.Urges Admissission of Psychological Distress Discovery 60 Days After Positive Ruling on Issue.Certificate of Svc Encl
ML19257B077
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 12/28/1979
From: Sheldon K
PEOPLE AGAINST NUCLEAR ENERGY, SHELDON, HARMON & WEISS
To:
Atomic Safety and Licensing Board Panel
References
NUDOCS 8001150198
Download: ML19257B077 (3)


Text

. ,

SM'Y/C

.o o,

4k=h :' $ \

3'Gq -;

UNITED STATES OF AMERICA M '% N NUCLEAR REGULATORY COMMISSION 4* i' BEFORE THE ATOMIC SAFETY AND LICENSING BOARD tk[tild)b

  1. ^

V V

j mi

)

METROPOLITAN EDISON )

COMPANY, ~~ ~~et al., ) Docket No. 50-289

) (Restart)

(Three Mile Island )

Nuclear Station, Unit )

No. 1) )

)

PEOPLE AGAINST NUCLEAR ENERGY MOTION TO CLARIFY OR CORRECT FIRST SPECIAL PREHEARING CONFERENCE ORDER In its First Special Prehearing Conference Order, the Board ruled that " General Discove::y shall be completed no more than sixty days after the service of this order." In its Order the Board acted upon most, if not all of the con-tentions, cther than those related to psychological dis-tress. However, it deferred ruling on the psychological distress contentions, the admissibility of which will be finally decided by the Commission.

The result is that parties with psychological distress contentions may not begin discovery on those issues for an unknown period of time, although general discovery ends in 60 days. PANE and other intervenors raising psychological distress contentions could be foreclosed from conducting discovery under the Board's timetable. We seriously doubt that the Board intended this result.

1745 023 s o 01150 / 9 8 (F

In order to assure an equitable opportunity for discovery on these issues, PANE moves that discovery on psychological distress and related contentions be allowed for at least sixty days from service of the Commission's ruling that the contentions must be heard in this proceed-ing.

Respectfully submitted, d [h "

Karin P. Sheldon SHELDON, HARMON & WEISS 1725 'I" Street, Suite 506 Washington, D.C. 20006 (202) 833-9070 Counsel for PANE Dated: December 28, 1979 1745 og4

=

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD

)

In the Matter of )

)

METROPOLITAN EDISON ) Docket No. 50-289 COMPANY, et al., ) (Restart)

)

(Three Mile Island )

Nuclear Station, Unit )

No. 1) )

)

CERTIFICATE OF SERVICE I hereby certify that a copy of " People Against Nuclear Energy Motion to Clarify or Correct First Special Prehearing Conference Order" were mailed postage prepaid this 28th day of December, 1979 to the following:

Secretary of the Commission ATTN: Chief, Docketing and Service Section U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Ivan W. Smith, Esquire Atomic Safety & Licensing Boarl Panel U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Dr. Walter H. Jordan 881 W. Outer Drive 1745 025 Oak Drive, Tennessee 37830 Dr. Linda W. Little 5000 Hermitage Drive Raleigh, North Carolina 27612 George F. Trowbridge, Esquire Shaw, Pittman, Potts & Trowbridge 1800 "M" Street, N.W.

Washington, D.C. 20006 James Tourtellotte, Esquire Office of the Executive Legal Director U.S. Nuclear Regulatory Commission Washington, D.C. 20555

/ ' k. V Karin P. Sheldon

.