Forwards Task Action Plan A-37, Turbine Missiles, & Rept Section on Overspeed Protection Sys.Requests Review & Editing of Rept Section on Overspeed Protection Sys, Incorporating Objectives of Task.W/O Encls
ML19257A984
Person / Time
Issue date: 03/13/1978
From: Boyle M
Office of Nuclear Reactor Regulation
To: Bosnak R
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-37, REF-GTECI-IT, TASK-A-37, TASK-OR NUDOCS 8001140173
Download: ML19257A984 (2)


Text

.

d p nacq %,'g

/

UNITED STATES j

NUCLEAR REGULATORY COMMISSION g

WASHINGTON, D. C. 20555 y

g e

A...../

March 13, 1978 MEMORANDUM FOR:

R. J. Bosnak, Chief Mechanical Engineering Branch Division of Systems Safety FROM:

M. L. Boyle, Task Manager Materials Engineering Branch

SUBJECT:

CATEGORY A TECHNICAL ACTIVITY NO. A-37, " TURBINE MISSILES" On February 8, M78, the Technical Activities Steering Comittee approved the content of, and the completion schedule for, the subject technical activity. As stated in the Task Action Plan, the Mechanical Engineering Branch has the lead responsibility for the Overspeed Protection System task and Subtask 2 under Probability of Missile Generation. Accordingly, MEB should allocate sufficient manpower to complete these tasks in the time allotted by the program schedule.

Enclosed is a copy of the approved version of the TAP (Enclosure 1) that shows the end products that are to be achieved by each task. Also enclosed is the latest version of the report section on the Overspeed Protection System (Enclosure 2). Enclosure 3 is an outline of recommended writing and editing guidelines that should be followed so that writing style will not differ significantly from section to section.

MEB is asked to review and edit the report section on Overspeed Protection Systems, and to write a final draf t of Subtask 2 of Probability of Missile Generation, following the writing and editing guidelines, and incorporating the objectives of each task, as outlined in the TAP, in the technical report.

In order that this technical activity remain on schedule, it is requested that MEB submit the final versions of these two report sections to the Task Manager by March 31, 1978.

M. L. Boyle, Task Manager Materials Engineering Branch Division of Systems Safety For enclosure & cc's, 1745 302 see attached sheet 00 a0

R. J. Bosnak

Enclosure:

As stated cc w/o enc 1:

R. J. Mattson, DSS J. P. Knight, DSS S. S. Pawlicki, DSS (E.B.Aycock,NRR M. L. Boyle, DSS 1745 303