Text
Alabama Power Company 600 North 18th Street Post office Box 2641 Birmingham, Alabama 35291 Telephone 205 323-5341 A
hbo%c'e' r";Oni AlabamaPower the southern electnc system M r 12, 1979 Docket No. 50-348 50--364 Director of Nuclear Reactor Ibgulation U. S. Nuclear Regulatory 0:xtmission Washington, D. C.
20555 Attention: Mr. Darrell G. P b nhut
Dear Mr. Eisenhut:
Attached for your infonnation is an updated schedule for fire protection nodifications for our Joseph M. Farley Nuclear Plant.
If you have any questions, please advise.
Yours very truly, F. L. Clayton, Jr.
FICjr/INF/nmb Attachment cc: Mr. R. A. Thomas Mr. G. F. Trowbridge l
a 1624 N7
/Joob s
lll 79m90 SSO F
IMPLEMENTATION DATES FOR PROPOSED MODIFICATIONS (STATUS AS OF 12-12-79)
Item Date Unit 1 Unit 2 1.
Sprinkler (All systems)
End of 2nd refueling Before fuel load outage Room 234, Area 16 Complete N/A 2.
Yard Hydrants' Complete N/A 3.
Portable Extinguishers Complete Before fuel load 4.
Hose Stations Complete Beforefuelloadl 5.
Smoke Detectors 9/1/80 9/1 /80 6.
UL Rated Doors Complete Before fuel load 7.
Penetration Seals 9/1/80 Before fuel load 8.
Portable Smoke Removal Complete N/A 9.
Term. Cabinet Water Complete Before fuel load Protection 10.
Dauper Rework End of 2nd Before fuel load refueling outage 11.
Eight Hour Battery Packs Complete Before fuel load 12.
Hose Stations in CTMT Complete Before fuel load 13.
RCP Oil Collection End of 2nd Before fuel load refueling outage 14.
Fire Pump Barriers Complete N/A 15.
DG Pot Transformer Complete Complete Circuit 16.
Barriers 9/1/80 9/1/80 17.
Inside Water Suppiy Complete Before fuel load 18.
HSP Suitch Relocation Enr' of 2nd Before fuel load retueling outage 1624 268' s97
IMPLDIENTATION DATES FOR PROPOSED MODIFICATIONS (STATUS AS OF 12-12-79)
Item Date Unit 1 Unit 2 19.
HSP Instrument Mods.
End of 2nd refueling Before fuel load outage 20.
Barriers in S. W.
Complete Complete Structure 21.
Fireproof Control Room Complete N/A Kitchen 22.
Modify New Fuel End of 2nd refueling N/A Storage Racks outage a (5 O 7