7590-01 NEGATIVE DECLARATION SUPPORTING ORDER FOR EXTENSION OF CONSTRUCTION COMPLETION DATES -

CONSTRUCTION PERMITS NOS. CPPR-118 AND CPPR-il9 GRAND GULF NUCLEAR STATION, UNITS 1 AND 2 MISSISSIPPI POWER & LIGHT COMPANY DOCKET NOS. 50-416 AND 50-417 The U.S. Nuclear Regulatory Commission (The Commission) has reviewed the ORDER relating to extension of construction permits CPPR-118 and CPPR-119 for Grand Gulf Nuclear Station, Units 1 and 2, located in Claiborne Ccunty, Mississippi. The construction permits are issued to the Mississippi Pcwer

& Light Company. The ORDER would authorize ex+ansion of the earliest and latest construction completion dates of Units 1 and 2 as follows:

Unit 1: From April 1,1979 and October 1,1979, to September 1,1980 and March 1, 1982.

Unit 2:

From October 1,1980 and April 1,1981, to April 1,1983 and October 1, 1984.

In accordance with 10 CFR Part 51, the Commission's Division of Site Safety and Environmental Analysis has prepared an environmental impact appraisal (EIA) for the ORDER. The Commission has concluded that an environmental inpact statement for this action is not warranted, because there will be no significant adverse environmental impacts affecting the quality of the human environment attributable to the proposed action in addition to those evaluated in the Commission's Ftnal Environmental Statement for Grand Gulf Nuclear Station Units 1 and 2 issued in August 1973, and currently experienced at that site. No significant

,}33b 7911150

7590-01 adverse incremental or cu'ulative impacts are expected to occur by extending the construction completion dctes. A negative declaration is' therefore appropriate.

The environmental impact appraisal is availabla for pub?ic inspection at the Commission's Public Document Room,1717 H Street, NW.

Washington, D.C.,

and at the local public document room located in the Claiborne County Courthouse, Port Gibson, Mississippi, 39150. A copy of the EIA may be obtained upon request addressed to the U.S. Nuclear Regulatory Commission, Washington, D.C., 20555, Attention: Director, Division of Site Safety and Environmental Analysis.

Dated at Bethesda, Maryland, this 30th day of October,1979.

FOR THE NUCLEAR REGULATORY COMMISSION

$x&a C d W 8 4 t i. d Ronald L. Ballard, Chief Environmental Projects Branch 1 Division of Site Safety and Environmental Analysis 1336 313