Provides Info Per Re NRC Review Status for Emergency Planning.Applicants Submittals Should Be by 791101 in Order to Complete Review.Hearing May Take Place in Jan 1980 If Schedule Followed
ML19254F970
Person / Time
Site: 05000471
Issue date: 10/29/1979
From: Beverly Smith
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
To: Callihan A, Cole R, Goodhope A
Atomic Safety and Licensing Board Panel
References
NUDOCS 7911190539
Download: ML19254F970 (2)


Text

NRC PUBLIC DOCUMENT ROOM

'k O

UNITED STATES

,(

,og

+

NUCLEAR REGULATORY COMMISSION s-f.

-i 3

a ec

,,E WASM NGToN. D. C. 20555

%v f y..

,' + Q.

-n s

a c/

October 29, 1979

.x

/

N Andrew C. Goodhope, Esq.

Dr. A. Dixon Callihan 3320 Estelle Terrace Union Carbide Corporation Wheaton, Maryland 20906 P. O. Box Y Oak Ridge, Tennessee 37830 Dr. Richard F. Cole Atomic Safety and Licensing Board U. S. Nuclear Regulatory Commission Washington, D. C.

20555 In the Matter of Boston Edison Company, g al.l (Pilgrim Nuclear Generating Station, Unit 2)

Docket No. 50-471 Gentlemen:

In accordance with my letter of October 23, 1979, I am providing the following in-formation concerning the status of the Staff's review of emergency planning for Pilgrim Unit 2.

If In a letter dated October 23,1973 --Emergency Preparedness Requirements - Pil-grim Nuclear Generating Station, Unit 2--the Staff informed the Applicants of the requirements necessary to complete the review of this proceeding on this subject.

The Staff does not know when the Applicants will submit the required information; however, the Staff believes much of it will be included in the revised emergency plans for Pilgrim Unit 1. The information for Pilgrim Unit 1 should be submitted on November 1,1979, and the Staff review will be completed in approximately three weeks. If the information submitted for Pilgrim Unit 1 is utilized by the Applicant fer Unit 2, then the completion of the evaluation for Unit 2 should be completed shortly after Unit l's review. Therefore, if this schedule is adhered to, there is a strong likelihood the Staff will be prepared to go to hearing in January,1980.

Of course, this will depend on the sufficiency of the Applicants'submittals and the actual time required to finish the review.

1/ This letter was distributed by the Staff to the Board and parties.

4 356 7911100

  1. The Staff will keep the Board and parties informed if this present schedule is sig-nificantly altered.

Sincerely,

")

Barry H. Smith Counsel for NRC Staff ec: George H. Lewald, Esq.

Dale G. Stoodley, Esq.

Henry Hermann, Esq.

Mr. and Mrs. Alan R. Cleeton The Board of Selectmen William S. Abbott, Esq.

Michael B. Meyer, Esq.

Mr. Lester B. Smith Francis S. Wright, Esq.

Stephen M. Leonard, Esq.

Patrick J. Kenny, Esq.

Laurie Burt, Esq.

Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Appeal Board Docketing and Service Section