Summary of 790709 Meeting of ACRS Subcommittee on Bailly Generating Station in Portage,In Re Acquisition of Technical Info Concerning Piling Program Proposed by Util
ML19254F958
Person / Time
Site: Bailly
Issue date: 08/08/1979
From:
Advisory Committee on Reactor Safeguards
To:
Advisory Committee on Reactor Safeguards
References
ACRS-1655, NUDOCS 7911190522
Download: ML19254F958 (12)


Text

MEETING DATE: 7/9/79 o e2 ISSUE DATE:

8/3/79

.(

m l

3l1d i MINUTES OF.THE ACRS SUBCCMMITTEE MEETING ON BAILLY GENERATING STATION, NUCLEAR 1 1

PORTAGE, IN

]([$ - ((

~d-JULY 9,1979 The Bailly Generating. Station, Nuclear 1 Subcommittee met on July 9,1979, at the Portage Holiday Inn, 6200 Melton Road, Portage, Indiana. The main purpose of the meeting was to acquire technical infomation from the NRC Staff and the Permittee (Northern Indiana Public Service Company) regarding the Permittee's proposed piling program.

Notice of the meeting was published in the Federal Register on June 22, 1979.

Copies of the notice, meeting participants, and schedule are included as Attachment 1, 2, and 3, respectively. A complete set of handouts and viewgraphs is kept in the ACRS Office, while a listing of these is included as Attachment 4 Request.s were made by five members of the public to make oral satements, and four of these also presented their statements in writing (see Attachment 4).

EXECUTIVE SESSION (2:00 cm - 2:05 pm)

Dr. Lawreski, Subcommittee Chairman, convened the meeting at 2:00 pm, introduced the ACRS members and consultants who were present; indicated that R. Muller is the Designated Federal Employee; and that the meeting would be conducted in accordance with the provisions of the Federal Acvisory Committee Act and the Government in the Sunsnine Act. This meeting was neld in response to a request from the Commission, dated June 8,1979, requesting the Committee to review any resultant design cnange and safety aspects of shorter pilings.

The notice of the meeting indicated that members of tne public may present only technical information, related to the design and function of the piles. He noted the presence of Mr. Rick Harris of U.S. Congressman Fithian's staff.

ACRS CONSULTANT REPORTS (2:05 pm - 2:10 pn)

(A site visit, not part of the Subcommittee or full Committee meeting, was conducted by NIPSCO for the two consultants before this meeting. NIPSCO also invited about 30 people of the press to this site visit.

R. Muller and P. Tam of the~ ACRS Staf' accompanied the two consultants.)

7911193Wd 1744 259

Bailly Nuclear 1 7/9/79 Both Drs. Richart and Scott stated it was too early to make a recort but that their concerns, if any, would emerge as the meeting progressed.

MEETING WITH NRC STAFF AND NIPSCO REPRESENTATIVES (2:10 pm - 4:15 pm)

Mr. M. D. Lynch M. D. Lynch, NRC Licensing Project Manager for Bailly, stated that NIPSCO sutrnitted a proposal (March 1978) to use shorter piles instead of using ones that would go all the way to bedrock. The Staff has not completed review of this T.roposal. He then gave a brief description of the licensing history of Bailly:

The Bailly application was submitted to the AEC in the summer of 1970, and a Staff Safety Evaluation Report (SER) was issued in February of 1972.

It was recognized in the Preliminary Safety Analysis Report (PSAR) that the sand and compressible clay at the site were not suitable for foundation material. NIPSCO had proposed that foundation piles would be used to eliminate the problem of differential settlement. The piles would go to till, or to bedrock, depending on the outcome of post-CP tests. Accord-ing to regulations at that time, the Applicant was not cermitted to perform significant pre-CP construction activities. The Staff was aware of this requirement and thus stated in its SER two criteria namely, that the piles be "non-displacement and "high capacity.

In the hearings in 1972 and 1973, the Applicant stated that the final design of the piling would be established after construction activities began. A CP was issued in May,1974.

In December,1975, NIPSCO indicated that they intended to jet their piles; but after the Staff observed the jetting of one, it stopped NIPSCO frem any further such activities in favor of more conventional methods. In March,1978, the Licensee subnitted the proposal to use shorter piles. An indicator pile program was initit.ted and a total of three reports were submitted. Staff review of these reports is continuing.

4 240

Sailly Nuclear 1 7/9/79 Mr. R. Bohn Mr. R. Bohn, Manager of the Nuclear Staff for NIPSCO, noted that five different pile types were mentioned in the PSAR but NIPSCO did not commit to any type, except to " principal architectural and engineering design criteria". These are: " Class I structures will be supported on pile foundations bearing on competent material," and " piles will resist downward, uplift,and lateral loads for all conditions of static and dynamic loading". Two coal-fired units (Units 7 and 8) on the same site are supported on concrete mats without piles. The maximum settlement observed is two inches. The nuclear unit would require pilings since its floor loading wouid be much greater than for the coal-fired units, and the seismic design is more rigid.

Mr. Sohn indicated that original attempts to drive piles through the surface layers were frustrated because of the very dense glacial lacustrine deposits.

Several different methods were tried and it was decided that the most efficient method was to use a vibrating hammer in conjunction with a high-pressure jet of water to puncture through these dense materials and get down to the glacial till. However, after the Staff had observed the operation, they stopped it on grounds tnat jetting may damage the soil around the piles and render the piles unsatisfactory, including being potentially unstable d ring a seismic event.

Subsequently, NIPSCO proposed to bed the piles in these very dense glacial lacustrine deposits instead of punching through them. An extensive indicator pile program was perforned which showed that piles fotnded in the glacial lacustrine deposits would satisfy the engineering and architectural design criteria with an adecuate factor of safety.

Dr. Scott asked if any settlement estimate was done for the reactor buildings if no piles are used. Mr. Xiefer replied that they never finalized any esti-mates; further, a nuclear reactor building would exert up to 10,000 psi pres-sure on the ground, compared to 3,000 psi by fossil fuel' plants. Settl ement characteristics between the two would be quited different.

Dr. Kerr asked why the Staff did not approve or disapprove NIPSCO's proposal to use jetting. Mr. Lynch said that the Staff, at the CP stage of licensing ga4 261

Sailly Nuclear 1,/9/79 a plant, addresses only the technical feasibility of a proposal. At the OL stage, the Staff would review the application in greater details. Therefore, the Staff merely "acq.ujesced" in the jetting proposal, but did disapprove it as more details were available.

Dr. Lawrcski asked if Mr. Lynch was aware of other nuclear plants which used short pilings.

Mr. Lynch said that he knew of only Fort Calhoun.

Mr. M. <iefer Kiefer of Dames and Moore described the soil sjructure of the site, Mr.

indicating that the interbedded layer (of very dense sand and hard clay) would be the structure which would support the piles. This layer is on the order of 50 to 70 feet in thickness. Piles will be driven to this layer and 5-20 feet into it to some specified resistance. The tops of the piles will be tied together by a heavily reinforced concrete mat, ranging in thickness from 5 to 12 feet. The piles will be emtedded three feet into the mat. In addition, very stiff shear walls would exist to dictate that the structures and their foundation will act as a rigid system. This will enable the struc-tures to settle uniformly.

Dr. Richart asked about the induced stresses as a result of forced uniform settling.

A. K. Singn of Sargent and Lundy replied that in tnefr design, they nave recognized the fact that the structure would redistribute scee of its loads due to settling.

Pile load tests were parformed on test piles and the ultimate capacities ranged from 490 to SCO tons, indicating that large margins of safety are provided.

A series of studies were also performed to evaluate foundation behavior in terms of lateral and uclift loads induced by the design basis earthquake. It was found that the bending moment dissipates within the top 20 feet of the piles.

Group lateral deflection would be less than 0.4 inch and is considered tolerable.

Mr. Kieffer concluded that t'cet piles may be installed by connonly-used techniques witnaut jetting, and that piles teated in the interbedded deposits affort a large margin of safety under static and dynamic conditions.

4 262

Bailly Nuclear 1 7/9/79 Dr. Richart asked for details of the new load tast procedure. Mr. Paulson of Sargent and Lundy described it as being in general accordance with ASTM D-1143.

During the test, ten-ton loads are added to a pile at 21/2-minute intervals until a total of 400 tons is reached. The 400 tons will remain on the pile for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and load deflection measurements for this period will be taken. Then additional 10-ton increments will be added at 21/2-minute intervals until 600 tons is reached or until pile failure. The Staff, however, has not completed review of this procedure.

Mr. D. Koutsoftas Mr. Koutsoftas of Dames and Moore addressed the " soft spots" densification program. " Soft spots" were made as a result of jetting activities and, to a lesser extent, extraction of test oiles. The nature of these spots vary with depth:

in the cohesionless (sand) layers, the material has been loosened, whereas in the interbedded layer, the disturbance is simply a hole left by pile ex traction. The Licensee has proposed to densify these spots by driving 10 3/4-inch diameter closed-end pipes into the soil, spaced 3 - 31/2 ft.

apart. These densification piles will be driven to penetrate below the depth influenced by preconstruction activities and to a resistance of 25 blows / inch.

Secondary and even tertiary densification piles will be driven to resistances of 10 blows / inch. The program is intended to be flexible and the quantity of densification piles required for each " soft spot" will be determined as the operation proceeds.

Dr. Siess was concerne: that the densification piles may not go deep enough and that production piles may be bedded in undensified material. Mr. Koutsoftas replied that load tests and borings may be performed to check the load capaci-ties and locations of these piles.

Mr. Lynch summarized for the NRC Staff. He stated that the " soft spots" issue, and efforts to densify them, are major concerns. The Staff is still reviewing the factors of safety, the corrosion report, uplift of piles and tolerances on piacement of piles.

17'4 263

Sailly Nuclear 1 7/9/79 STATEMENTS BY THE PUBLIC (t:15 ;xn - 4:40 pm)

A total of four memeers of the oublic requested, prior to the meeting, to make oral presentaticns. All four have also submitted written statements and tnese are kept in the ACRS Office files.

fir. H. p. Read Mr. Read is an architect by training and professien and was speaking as an interested citizen with design and construction experience and familiarity with the Sailly licensing history. He said that a " safe structure is " safe" only as long as the assumptions made hold true. He noted the wide difference between theory and reality, and has himself experienced the results of the difficulty of soils analysts to accurately predict strata behavior, particu-larly the potential for liquefaction. He believed that during the licensing and intervention stage of Bailly, NIPSCO and the Atomic Safety and Licensing Board both made the representation that the piles would go all the way ta bedrock.

Construction began with the intention to drive piles to bedrock but the intention was changed after difficulty. in pile driving was encountered.

He stated that during the intervention, while discussing seismicity contentions, the NRC Staff witness said that his review extended only to the integrity of tne reactor building itself without spending effort to investigate differential movement between ouildings and between a building and the piping wnich penetrates its foundations. There is thus a lack of analysis on the system as a whol3 for differential movements among buildings and structures. During an eartncuake, for example, differential movement between the reactor building and the cooling tower may result in breakage of the cooling water piping.

The strata at the Sailly stie is complex, as test borings show. Such ccmplexity is exemplified by the variation in thickness by some 70 ft. of tne lacustrine sand / clay deposit. Thus, according to Appendix A of 10 CFR Part 100, wnich pro-vides that " Additional investigations and/or more conservative determinations

... may be required for sites located in areas having cc plex geology or in areas of high seismicity", the Subcomittee should rec:xnmend that the NRC require additional investigation and more conservatism in foundation design.

17^4 2<'

Sailly Nuclear 1 7/9/79 On seismicity of the region, he claimed that evidence of faults could easily be hidden by the sand, and that current mapping of faults ends at the water line. One is not sure of the distance between Bailly and a fault line. Thus, the distances assumed in the Operating Basis Earthquake analysis is of question-able validity.

He showed concern about the truthfulness of the information supplied by NIpSCO and tne lack of diligence of the NRC Staff to verify Applicant-supplied informa-tion. He illustrated his opinion by stating that neither the Staff nor the Apolicant could, in the evidentiary hearing, point' out how population distribu-tion around the site was determined and the population data was totally " fictitious."

(Note:

In a subsequent phone conversation with the Staff site analyst, E. Markee, on this allegation, I found that the licensee's population figures were obtained from the Bureau of Census.

W. Nischan, currently retired from the Staff, did verify that the licensee's figures are in substantial agreement with the Sureau of Census data, p. Tam)

Mr. T. Weinbero, Co-Chaircerson of Sailly Alliance Mr. Weinberg acknowledged that he based nis views on common sense. He pointed out that the Bethlehem Steel Plant next door has " terrible settling problems" and claimed that Bailly would have the same problems. His major concern was settling of the plant causing stress and rupture in pipes carrying water to and from the cooling tower. He and his Alliance wanted an evidentiary hearing on this matters.

Mr. G. Wilson, Local 5737 Mr. Wilson's Local represents 5800 production and maintenance workers at Setnlehem Steel's Burns Harbor plant. Most of the steel plant lies within the LPZ of Bailly, and a number of buildings and structures have suffered settlement problems.

(Note: Mr. Wilson claimed that these are on short pilings but D. Lynch, NRC Project Manager, has checked with Sethlehem Steel and concluded that these are actually built on spread footings over sand compacted to 75%.) Mr. Wilson was also concerned about emergency evacuation of the area resulting in loss of all employees of the steel plant, leading to severe physical damage to the plant.

(No te : Emergency

'4 265

Bailly Nuclear 1 8-7/9/79 Planning relating to Bethlehem Steel has been discussed by the Committee in its 147th meeting, July 13 and 14,1972).

Mr. 01szanski, Local 1'010

~

Mr. Olszanski spoke for his Local and District 31 Chicago and Northwest Indiana District of Steel workers. He expressed concern about evacuation as Mr. Wilson did, and indicated a general distrust of engineers. He wanted an evidentiary hearing to cross-examine the Licensee on his proposal, but acmited that he did not understand the technical matters persented.

Mr. T. Escate Dr. Lawreski asked if anyone else in the public would like tc be heard. Mr. Esgate thus stated that NIPSCO has undermined the Sailly foundation by jetting, and that such should be cause for a new hearing.

EXECUTIVE SESSICN (4:40 pm - 4:50 pm)

Dr. Richart showed continued concern for tne " soft spots", especially the identi-fication of their extent and charac+. eristics. Dr. Siess asked the Staff to address the nature of the foundation at the steel plant and settlement problems in the full Ccanittee meeting. Dr. Lawroski emphasized that the Staff and NIPSCO address the subject of soil softening and corrective measures.

Whereupon, at 4:55 pm, tne Subcommittee meeting was adjourned.

1.......

NOTE: A transcript of portions of the meeting is on file at the NRC Public Document Room at 1717 H Street, NW, Washington, DC or can be obtained from Ace-Federal Reporters, Inc., 444 North Capitol Street, Washington, DC 20001 (202-347-3700).

17e4 266