Responds to NRC Re Environ Qualification of IE Instrumentation & Electrical Equipment.Submits Schedule for Providing qualification-related Data.Details Re Schedule for Conducting Investigation Will Be Provided by 791207
ML19254F887
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 11/13/1979
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: Rubenstein L
Office of Nuclear Reactor Regulation
References
NUDOCS 7911190349
Download: ML19254F887 (1)


Text

TENNESSEE VALLEY AUTHCRITY CH ATT A NOCG A. TENN E5S Ec 3'4C' 400 Chestnut Street Tower II November 13, 1979 Director of Nuclear Reactor Regulation Attention:

Mr. L. S. Rubenstein, Acting Chief Light Water Reactors Branch No. 4 Division of Project Management U.S. Nuclear Regulatory Commission Washington, DC 20555

Dear Mr. Rubenstein:

In the Matter of the Application of

)

Docket Nos. 50-327 Tennessee Valley Authority

)

50-328 We have received your October 17, 1979, letter to H. G. Parris on the subject of " Environmental Qualification of Class IE Instrumentation and Electrical Equipment." TVA was requested to provide additional informa-tion on Sequoyah Nuclear Plant addressing the two items specified in your enclosure.

The NRC requested in item 1 that TVA provide a table listing all Class IE safety-related equipment and appropriate qualification-related data for this equipment. This table would include all equipment located both inside and outside of containment including balance-of-plant and nuclear steam system supplied equipment. TVA will provide this information according to the following schedule.

Equipment inside containment January 11, 1980 Equipment outside containment 1.

Which could be subjected -

February 15. 1980 to adverse environment (RELB) 2.

All other equipment April 1, 1980 The NRC requested in item 2 that TVA conduct an evaluation of electrical equipment to define a list of materials which have the potential of significant aging mechanisms.

TVA is engaged in an industrial effort to develop a consistent and meaningful approach to this_ investigation.

The details concerning the schedule for conducting the investigation and submitting a report will be provided by December 7, 1979.

Very truly yours, TENNESSEE VALLEY AUTHORITY

(

\\

\\

L. M. Mills, Macager Nuclear Regulation and Safety 7 91119 a ia <F-7