f;%% ConSum8IS d
D Power L,j Company
% :p q
W General Offices: 212 West Mich.gan Avenue, Jackson, Michigan 49201 e Area Code 517788-0550 October 25, 1979 Director, Nuclear Reactor Regulation Att Mr Dennis L Ziemann, Chief Operating Reactors Branch No 2 US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT - FIRE PROTECTION MODIFICATIONS: ALTERNATE SHUTDOWN PANEL Consumers Power Company letter dated August 24, 1979 requested approval of a delay in the required implementation da'.e for an item specified in the Fire Protection Safety Evaluation Report for Big Rock Point.
Specifically, delay in the implementation of the alternate shutdown panel was requested to permit this modification to be incorporated into the Systematic Evaluation Program integrated assessment. Consumers Power Company stated that prompt approval was necessary to prevent unnecessary effort under the existing contract for fire protection modifications at. Big Rock Point.
In telephone conversations with memisers of the NRC staff, Consumers Power Company has been informed that higber priority work will preclude prompt NRC action.on our request to delay the required implementation of the alternate shutdown panel modification. Consumers Power Company notes, however, that delay of this modification has previously been approved by the NRC for other plants involved in the Systematic Evaluation Program, and that the bases for these approved delays are similar to the basis for the requested delay at Big Rock Point. Accordingly, Consumers Power Company expects that our request w'ill be approved at such time as the NRC is able to act upon it.
Work on the proposed alternate shutdown panel has proceeded through the Engineering phase, and our contractor is ready to award bids for the procurement of the equipment. Awarding of such bids would result in unrecoverable expense should panel design be significantly changed as a result of interfaces with SEP. For this reason and in consideration of the expected approval of our request for implementation delay discussed above, Consumers Power Company has directed our contractor to suspend efforts related to procurement of equipment for the alternate shutdown panel.
This action may preclude meeting the established implementation date of October 1980.
It is, 1233 062 7 9103 00 d F
2 therefore, important that Consumers Power Company be promptly notified if our request for implementation delay will not be granted.
David A Bixel (fr.gned)
David A Bixel Nuclear Licensing Administrator CC JGKeppler, USNRC 1238 063