Responds to IE Bulletin 79-23, Potential Failure of Emergency Diesel Generator Field Exciter Transformer. Util Has Not Contracted for Diesel Generators Pending NRC Review of Pile Placement Methodology
ML19254D270
Person / Time
Site: Bailly
Issue date: 09/27/1979
From: Shorb E
NORTHERN INDIANA PUBLIC SERVICE CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NUDOCS 7910230260
Download: ML19254D270 (1)


Text

,

[NIPECU Em 9 ~ Nortshern Indiana Public Service Company General Offces l 5265 Hohman Avenue l Hammond. Indiana 4CG25 l Tel:853-5200(219) 5 EUGENE M. SHORB riau v cc acsmem Se ptember 27, 1979 Mr. Jame s G. Keppler United States Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137

SUBJECT:

IE Bulletin No. 79-23 " Potential Failure of Emergency Diesel Generator Field Exciter Transformer" Dated September 12, 1979

Dear Mr. Keppler:

Northern Indiana Public Service Company (NIPSCO) has not yet con-tracted for the purchase of the Emergency Diesel Generators for Bailly Generating Station Nuclear I.

Work cn N1PSCO's Bailly Generating Station Nuclear I is presently halted, pendhg completion of NRC review of NIPSCO pile placement methodology. There will be no additional procurement of components or material until pile placement is resumed.

However, we have advised our Consulting Engineers of the design error in the emergency diesel generators at the Florida Power and Light Com-pany's Turkey Point facility and advised them to take all action necessary to avoid such errors on the Bailly Ciesel generator design.

Very truly yours, A

EMS:bw cc: U. S. Nuclear Regulatory Commission g }g]

Office of Inspection and Enforcement Division of Reactor Operations Inspection i J

Washington, D. C. 20555 s'