Notification of 791204-05 Meeting W/Util in Clinton,Il to Assess Const Status
ML19253C658
Person / Time
Site: Clinton Constellation icon.png
Issue date: 11/26/1979
From: Buckley B
Office of Nuclear Reactor Regulation
To: Stolz J
Office of Nuclear Reactor Regulation
References
NUDOCS 7912060652
Download: ML19253C658 (4)


Text

4 mi pR Rf Cgfg

/

'o, UNITED STATES E

'j NL' CLEAR REGULATORY COMMISSION 3

g wommonw oeM*w 9,,

,/

NOV 3 613/J

++,..

Docket No. 50-461 MEMORANDUM FOR: John F. Stolz, Chief, Light Water Reactors Branch No. 1, DPM FROM:

Bartholomew C. Buckley, Project Manager, Light Water Reactors Branch No. 1, DPM

SUBJECT:

FORTHCOMING SITE VISIT AT THE CLINTON NUCLEAR GENERATING STATION DATE:

December 4 & 5, 1979 LOCATION:

Construction site near Clinton, Illinois PURPOSE:

Site visit by Caseload Forecast Panel to assess the status of construction.

Proposed agenda is enclosed.

PARTICIPANTS:

NRC B. Buckley B. Lovelace R. Muranka R. Knop Illinois Power Company G. Wuller G. Brashear B,C.BJ Bartholomew C. Buckl Project Manager Light Water Reactors Branch No. 1 Division of Project Management

Enclosure:

Agenda cc:

See page 2 1506 195 7912060 6

\\

1 NOV 2 61979 Mr. L. J. Koch Mr. L. J. Koch, Vice President Illinois Power Company 500 South 27th Street Decatur, Illinois 62325 cc: Mr. Peter V. Fezio, Jr.

=-

Schiff, Hardin & Waite 7200 Sears Tower g

233 30uth Wacker Drive Chicago, Illinois 60606 Mr. George Wuller Licensing Coordinator Illir.ois Power Company 500 South 27th Street Decatur, Illinois 62525 r

u r-.

hb ij

[-J.:

1506 196 L=

ip

.e....

_I-

3 j

t i

ENCLOSURE CLINTON POWER STATION, UNIT NO. 1 CASELOAD FORECAST PANEL SITE VISIT AGENDA 1.

Overview of project construction schedule including construction progress, major milestones completed, current problems and antici-pated problem areas and schedule for licensing.

2.

Current status of bulk quantities for Unit 1 and r.eeded common facility including current total estimated quantities, quantities instalied to date, quantities scheduled installed to date, current percent complete for each and average installation rates.

Discussion or progress since June 12, 13, 1979 site visit.

a.

Concrete (CY) b.

Process Pipe (LF)

- Large Bore Pipe 2 1/2" and larger

- Small Bore Pipe 2" and smaller c.

Yard Pipe d.

Large Bore Hangers, Snubbers, etc. (ea) e.

Small Bore Hangers, Snubbers, etc. (ea) f.

Cable tray (LF) g.

Conduit (LF) h.

Cable (LF) 1.

Terminations (ea) j.

Circuits (ea) k.

Instrumentation 3.

Current status of pipe hangers, snubbers, restraints, etc., including design, fabrication, delivery and installation.

4.

Current status of preop tests procedure writing, integration of preop testing activities with construction schedule, system turnover schedule, preop testing and current preop test program banpower.

5.

Review of schedule identifying critical path items, amount of float for various activities, the current critical path to Fuel Loading and methods for implementation of corrective action for activities with negative float if any.

6.

Estimated percent complete for Unit 1 and needed common facility as of December 1, 1979.

1506 197

I i

2-7.

Site tour and observation of construction activities.

8.

Current status of design / engineering activities.

9.

Procurement management and current status of major components including hangers, snubbers, pipe whips, valves, piping and etc.

10. Actual and proposed craf t work force, craft availability, productivity, potential labor negotiations and problems.

9 1506 198