UNITED STATES 8
g p,
NUCLEAR REGULATORY COMMISSION g
E WASHINGTON, D. C. 20555
\\ */
oon nn Docket Nos.: 50-329 50-330 MEMORANDUM FOR: Steven A. Varga, Acting Assistant Director 3
for Light Water Reactors Division of Project Management FROM:
Darl Hood, Project Manager, Light Water Reactors Brarich No. 4, Division of Project Management k.
THRU:
L. S. Rubenstein, Acting Chief, Light Water.Reaptors Branch No. 4, Division of Project Management
SUBJECT:
REVISED ESTIMATE OF' CONSTRUCTION COMPLETION DATE FOR MIDLAND The visit by the NRC staff's Caseloaa Forecast Panel on September 18-19, 1979, to the site for Midland Plant, Units 1 & 2, has resulted in a further slip in the Panel.'s projected completion date for Midland Unit 2.
The Panel.'.s revised estimate for completion of Unit 2 (the first of the Midland units scheduled for completion) is Junc 1982. As indicated in previous letters to the hearing boards for previous projections by the Panel, schedular estimates for this plant, although only a rough indication, could potentially be relevant and material to the Midland proceedings. Accordingly, I rsommend that both the remand and OL boards be informed of the revised estimate by the Panel.
The revised estimate of June 1982 for Unit 2 completion represents a seven-month slip in the Panel'-s previous estimate of November 1981* **. The applicant /.s current estimate is June 1981***.
However, the applicant is t
currently developing a revised forecast (Forecast No. 6) to reflect recent increases in electrical quantities and the influence of TMI-2 issues and open licensing issues. Forecast No. 6 will be finalized in January 1980.
The estimate by the Forecast Panel does not include TMI-2 effects and is
.f based principally upon the observed status of Midland construction coupled with the experience of previous plants at this construction stage.
Docunentation of the September 18-19, 1979 nieeting summary is in progress.
J Copies will be forwarded upon canpletion.
e o[
Darl Hood, Project Manager Light Water Reactors Branch No. 4 Division of Project Management R. Hoefling letter to Remand Board dated May 31, 1979 R. Hoefling letter to OL Board dated May 21, 1979 Michael I. Hiller letter to OL Board dated June 20, 1979
~