Commonwealth Edison
. One First Nabonal Plaza, Chicago, tilino:S Address Reply to: Post Office Box 767 Chicago, Ilhnois 60690
~
September 21, 1979
/
Mr. James G.
Keppler, Director Directorate Gf Inspection and Enforcement - Region III U.S. Nuclear Regulat.ry Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137
Subject:
LaSalle County Station Units 1 and 2 Supplemental Response to IE Inspection Report Nos. 50-373/79-24 and 50-374/79-17 NRC Docket Nos. 50-373 and 50-374 References (a):
J. G.
Keppler letter to B.
Lee, Jr.
dated September 15, 1979 (b) :
C. Reed letter to J. G.
Keppler dated August 10, 1979
Dear Mr. Keppler:
We ara in receipt of your acknowledgement (Reference (a))
of the Commonwealth Edison response to the subject IE Inspection Reports.
We understand the position stated in that acknowledgement and have no comment relative to the issues or schedule discussed.
We recognize that the actions of Commonwealth Edison relative to the certification of N-5 Forms was not in strict agreement with the applicable engineering procedure and that such deviations must be prevented from recurring.
In that regard, the corrective action outlined in the response to the subject Inspection Reports will be completed on the schedule previously defined in Reference (b).
If you have any further questions in this regard, please direct them to this office.
Very truly yours, L<.f D.
L.
Peoples Director of Nuclear Licensing LOD:mae L
i.