Responds to NRC Re Violations Noted in IE Insp Rept 50-358/79-06.Corrective Actions:Moved Responsibility for Entire Flushing Program within One Dept
ML19253B456
Person / Time
Site: Zimmer
Issue date: 08/22/1979
From: Borgmann E
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19253B453 List:
References
QA-1189, NUDOCS 7910160204
Download: ML19253B456 (2)


Text

Of k ?g* 3

~

~

THE CINCINNATI GAS & ELECTRIC COMPANY as F Ct N CINN ATI. OHIO 45208 vict en ior August 22, 1979 QA-ll89 U. S. Nuclear Regulatory Comission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attention: Mr. J. G. Keppler, Director RE: WM. H. ZIMMER NUCLEAR POWER STATION - UNIT I IE INSPECTION REPORT N0. 79-06, CONSTRllCTION PERMIT N0. CPPR-88, DOCKET NO.59-358, W.0. #57300-957, JOB E-5590 Gentlemen:

This letter supplements our formal reply to the subject inspection report.

It is our opinion that nothing in this letter is prcprietary.in nature.

We wish to supplement the Corrective Action to be Taken to Avoid Further Noncompliance portion of the reply to Item la as follows:

Procedures SU. ACP.02, Preparation of Flushing Procedures, and SU. ACP.03, Conduct of Flushing, are being modified to transfer responsibility for verification of boundary valve position and tagging from the General Engineering Department QA&S Section to the Electric Production Department QC Group.

This change will vest responsibility for the entire flushing program within one department, j

The Electric Production Department Quality Engineer will establish witness points on the initial valve line-up in the " official" copy of flushing procedures which have not been started, and, as appropriate on documented deviations to flushing procedures, The QA&S Section will perform audits to assure that these commitments are fulfilled, g

nx w am

Mr. J. G. Keppler, Director

d. S. Nuclear Regulatory Commission Region III QA-ll89 - August 22, 1979 Page 2 Date When Full Compliance will be Achieved Full compliance to this procedure will be achieved by September 1,1979.

We trust that you will find this supplement acceptable.

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY By 7"

E. A. BORGMANN SENIOR VICE PRESIDENT RLW:pa O/3 8

~

s

.