ML19250A632

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-518/79-17,50-519/79-17,50-520/79-17 & 50-521/79-17 on 790814-17.No Noncompliance Noted.Major Areas Inspected:Steel Structures & Supports,Welding Activities & Response to Previous Insp Findings
ML19250A632
Person / Time
Site: Hartsville  Tennessee Valley Authority icon.png
Issue date: 09/11/1979
From: Blake J, Herdt A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19250A623 List:
References
50-518-79-17, 50-519-79-17, 50-520-79-17, 50-521-79-17, NUDOCS 7910240096
Download: ML19250A632 (4)


See also: IR 05000518/1979017

Text

/

'o

UNITED STATES

8

g

NUCLEAR REGULATORY COMMISSION

o

g

a

REGION 11

'

o

101 MARIETTA ST

N.W.. sulTE 3100

e*

ATLANTA, G EORGIA 30303

.....

Report Nos. 50-518/79-17, 50-519/79-17, 50-520/79-17, and 50-521/79-17

Licenset: Tennessee Valley Authority

500A Chestnut Street

Chattanooga, Tennessee 37401

Facility Name: Hartsville

Docket Nos. 50-518, 50-519, 50-520, and 50-521

License Nos. CPPR-150, CPPR-151, CPPR-152, and CPPR-153

Inspection a

sv'll

uclear Plant near Hartsville, Tennessee

Inspector:

'/ o

79

J.

.

lake

/

Date Signed

l

/ f7

Approved by.

A. R. Herdt, Section Chief, RCES Branch

'Date Signed

SUMMARY

Inspection on August 14-17, 1979

Areas Inspected

This routine, unannounced inspection involved 26 inspector-hours onsite in the

areas of steel structures and supports - observation of welding activities;

previous inspection findings; and licensee identified items.

Results

Of the three areas inspected, no items of noncompliance or deviations vere

identified.

1202 272

.

-

bh

'

O*

7 910240 V

.

.

DETAILS

1.

Persons Contacted

Licensee Employees

R. T. Hathcote, Project Manager

  • W. R. Brown, Construction Engineering, STRIDE
  • W. T. Quinn, Construction Engineering, BOP
  • G. A. Gonsalves, Construction QA
  • H. S. Sheppard, Assistant Construction Engineer, QC, STRIDE
  • E. D. Peoples, Assistant Construction Engineer, QC, B0P
  • W. O. Brown, Assistant Construction D,gineer, Engineering Services
  • J. T. McGehee, Administrative Assis*,nt, STRIDE
  • S. P. Stagnolia, Welding QC Unit Supervisor, STRIDE
  • M. D. Gorman, Welding QC, BOP
  • H. H. Jones, Construction
  • L. A. Wilson, Construction

Other licensee employees contacted included several construction craftsmen,

QA and QC technicians, and engineers.

  • Attended exit interview.

2.

Exit Interview

The inspection scope and findings were summarized on August 17, 1979 with

those persons indicated in Paragraph 1 above. The inspector discussed the

licensees actions regarding corrective action for the construction defi-

ciency report concerning the anchor chair welds described in Paragraph 5.

3.

Licensee Action on Previous Inspection Findings

(Closed) Noncompliance 50-518, 519, 520, 521/79-12-01, Outdated QA Program

Description. The licensee has revised the QA Manual to delete CEP-2.01.

(Closed) Noncompliance 50-518, 519, 520, 521/79-12-03, Welding Control

Procedures do not clearly define requirements. The licensee has prepared

and implemented a standard operating procedure nq, SOP-34, " Weld Inspection

Documentation" which provides the guidance requirements for inspection and

documentation of welding operations.

4.

Unresolved Items

Unresolved items were not identified during this inspection.

5.

Licensee Identified Items

On August 2,1979 the licensee reported that rejectable weld def-iciencies

had been identified in previously QC accepted welds in Units A-1 (50-518)

and B-1(50-520). The deficiencies involved weld size, undercut, and weld

1202

273

-2-

.

surface condition. The welds involved were fillet welds attaching

stiffener plates to the containment wall and base plate. TVA reported that

all of these welds would be reinspected and the QC inspectors involved

would be retrained.

At the time of the NRC inspection licensee QA } ersonnel were just complet-

ing the final reinspection of the anchor chair fillet welds.

The inspector observed the visual inspection activity by the TVA QA inspec-

tors; reviewed a sampling of the data gathered during the reinspection;

reviewed the requalification training program being conducted by the QA

training facility for the QC inspectors involved; discussed the problem

with QA and welding engineering unit personnel; and visually inspected

approximately thirty of the welds that had been rejected during the

rei:,spection effort.

The inspector informed the licensee that due to the nature of the most

predominant rejectable indications - undersize welds, weld undercut, and

surface condition problems such as arc strikes and surface irregularities,

it appeared that the corrective action of retraining the QC inspectors was

only treating a part of the problem.

(Welds with the deficiencies listed

above should not have been presented for final QC inspection).

Therefore

consideration would have to be given to providing training to the welders

and their supervisors concerning visual acceptance criteria for welds, and

this matter discussed in the final 50.55(e) report.

For tracking purposes this item was assigned number 50-518/79-17-01, and

50 520/79-17-01, " Containment Anchor Bolt ' Chair Weld' Deficiencies".

6.

Inspector Followup Items

(0 pen) IFI No. 50-518, 519, 520, 521/79-12-04, QA Training Program for

Welders.

The inspector noted the QA training plan still povides for

16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> of training for welders. Because of the nature of the construc-

tion deficiency discussed in paragraph 5 above, the inspector informed the

licensee that this item concerning QA training would remain open pending

completion of the work on the anchor chairs.

7.

Steel Structures and Supports - Observation of Welding Activities Within

Containment

The inspector observed welding activities in the Unit A-1 anc B-1 contain-

ments. The welding observed included the following:

A.

Welding of the vent tube structure to the containment base plate (Unit

A-1).

B.

Stainless steel cladding of several vent tube structure vertical seams

(Unit A-1).

.

1202 274

.

.

-3-

4

C.

Repair Welding of Unit A-1 Reactor Vessel Pedestal.

D.

Welding and grinding of anchor chair fillet welds in Unit B-1.

The inspector fo nd that the level of activity in the welding of safety

related structures was low due to the majority of the welding QC inspectors

being retrained.

There were no items of noncompliance or deviations in this area of inspec-

tion.

.

e

e

e

O

'

)%LUL

- >

'

'

. -. --

. - . .....

. _.

. .

_ _ _ ____