ML19249E930

From kanterella
Jump to navigation Jump to search
Ack Receipt of Petition by Citizens Against Nuclear Power Requesting NRC to Issue Order Revoking Facility CP Pending Design Change Review
ML19249E930
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 09/13/1979
From: Harold Denton
Office of Nuclear Reactor Regulation
To: Kodner J
CITIZENS AGAINST NUCLEAR POWER
Shared Package
ML19249E931 List:
References
NUDOCS 7910020715
Download: ML19249E930 (1)


Text

1

- ~ -

l

  • 4}"%

o, UNITED STATES i

! ', c.c ' 7.

NUCLEAR REGULATORY COMMISSION l

2 E

WASHINGTON. D. C. 20555 kN"'#

J SEP 131979 6

i Do'cket !io. 50-373

  • i 50-374 l

t Jan L. Kodner, Esq.

Citizens Against Nuclear Powr, et al.

l 230 West Monroe Street l

Suite 2026 Chicago, Illinois 60606

Dear Ms. Kodner:

i This letter is sent to acknowledge receipt of your petition on behalf of,

Citizens Against Nuclear Power, et al. requesting that the Director of the Of fice of Nuclear Reactor Regulation and/or the Director of the Office of Inspection and Enforcement issue an order that the construction pemit for Commonwealth Edison Company's LaSalle County Nuclear Power Station be sus-i pended and/or revoked untti confimatory review of certain design changes are completed. Your petition has been referred to the Director of the Office of Nuclear Reactor Regulation because the subject matter of the petition is within the jurisdiction of this office.

Your petition is being treated under 10 CFR 2.206 of the Comission's regulation, and accordingly, appropriate action will be taken on your peti-tion within a reasonable time.

I enclose for your information a copy of the notice that is being filed for publication with the Of fice of the Federal Register.

Si ncerely, f

c.

! vt -

^-

Harold R. Denton, Director Office of Nuclear Reactor Regulation

Enclosure:

As Stated

\\ 015 5 A 5

& 910020 7/73