Notification of 790821-22 Meeting W/Util in Port Gibson,Ms to Discuss Overall Project Status & Detailed Project Schedule.Will Observe Const Activities in Progress to Evaluate Facility Fuel Load Date.Discussion Topics Encl
ML19249A957
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 08/06/1979
From: Thomas C
Office of Nuclear Reactor Regulation
To: Stolz J
Office of Nuclear Reactor Regulation
References
NUDOCS 7908240666
Download: ML19249A957 (3)


Text

FC/

A-l~ bb

/ EQD p >" "' %

UNITED STATES y

NUCLEAR REGULATORY COMMISSION g.'

,(

( g W ASHINGT ON. D. C. 20555

\\...(.

  • AUG G 1979 Docket Nos: 50-416 and 50-417 MEMORANDUM FOR: John F. Stolz, Chief, Light Water Reactors Branch No.1, DPM LP

'/

Cecil 0. Thomas, Prject Manager, Light Water Reactors Branchho.1, DPM FROM:

SUBJECT:

FORTHCOMING CASELOAD FORECAST PANEL SITE VISIT (GRAND GULF NUCLEAR STATION, UNITS 1 AND 2)

DATES:

August 21-22, 1979 TIME:

9:00 a.m.

LOCATION:

Grand Gulf Nuclear Station Site, Port Gibson, :lississippi PURPOSE:

To discuss overall project status and detailed project schedule and to observe construction activities in progress in order to evaluate Unit 1 fuel load date.

PARTICIPANTS:

Mississippi Power & Light Company J. McGaughy L. Dale A. Zaccaria et al Nuclear Regulatory Commission W. Lovelace J. Rausch, Region II C. Thomas MATTERS TO BE CONSIDERED:

See enclosure CaeE O. Og6w-a-Cecil 0. Thomas, Project Manager Light Water Reactors, Branch No.1 Division of Project Management

Enclosure:

Matters to be Considered C

cc:

q 3

c See next page 7908240 M

ENCLOSUr.E MATTERS TO BE CONSIDERED AUGUST 21-22, 1979 SITE VISIT GRAND GULF NUCLEAR STATION, UNITS 1 AND 2 1.

07erview of construction progress since June 1, 1978, including construction progress, major milestones completec, current problems and any anticipated problem areas.

2.

Review of current status of design and engineering efforts including any potential problems that may arise.

3.

Review and current status of procurement activities.

4.

Review of actual cnd propased craft wcrk force, craft availability, produc-tivity, potential labor neptiations and problems.

5.

Review and current status of bulk quantities for Unit 1 and needed common facility including current total estimated quantities, quantities installed to date, quantities scheduled installed to date, current percent complete for each and average installation rates.

(A) Concrete (CY)

(B) Process Pipe (LF)

- Large pipe 2\\" and larger

- Small pipe 2" and smaller

()

Yard pipe (LF)

(D) Large Bore Hangers, Restraints, Snubbers, etc. (ea)

(E) Small Bore Hangers, Restraints, etc. (ea)

(F) Cable Tray (LF)

(G) Conduit (LF)

(H) Cable (LF)

(I) T<mninations (ea)

(J) Circuits (ea)

(K)

Instrumentation 7'b l.

. 6.

Detailed review and current status of pipe hangers, snubbers, restraints, etc., including design, fabrication, delivery and installation.

7.

Review and current status of preop tests procedure writing, intergration of preop testing activities with construction schedule, systems turnover schedule, preop testing and current preop test prograi manpower.

8.

Review of construction schedule identifying critical path items, amount of float for various activities, the current critical path to Fuel Loading and methods for implementation of corrective action for activities with negative float if any.

9.

Estimated precent complete for Unit 1 and needed common facility as of August 1, 1979.

10.

Site tour and observation of construction activities.