Notice of Deviation from Insp on 790424-27
ML19247B468
Person / Time
Issue date: 05/15/1979
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19247B461 List:
References
REF-QA-99900026 99900026-79-1, NUDOCS 7908090109
Download: ML19247B468 (2)


Text

SWEPCO Tube Corporation Docket No. 99900026/79-01 Notice of Deviations Based on the results of an NRC inspection conducted on April 24-27, 1979, it appears that certain of your activities were not conducted in full accordance with NRC requirements as indicated below:

Criterion V of Appendix B to 10 CFR 50 requires that activities affecting quality shall be prescribed by documented procedures and shall be accom-plished in accordance with these procedures.

A.

The QA Manual, Section 5, paragraph " System of Production Checks,"

states in part, "The machine settings and all pertinent data are.

in accordance with the welding procedure."

Contrary to the above, the welding performed in the manufacture of SA-312, T-304, ASME Code Class 1 and 2 piping was not accomplished in accordance with welding procedure specification (WPS) H-304-HN, Revi-sion 4, as required by the job order travelers, for the following orders:

Weldir.g Procedure Specification H-304-HN, Revision 4 Amps Range 160-220 Shielding Gas Flow, CFH 40 (Both Torches)

Travel Speed, IPM 8-9 Job No. M-3225-8 Top Torch Bottom Torch Amps Used 250 260 Job No. M-3536-9 Amps Used 280 275 Shielding Gas Flow, CFH 60 60 Travel Speed, IPM 4

4 7