ML19247B024

From kanterella
Jump to navigation Jump to search
Submits Info Justifying Heat Removal Adequacy of Air Recirculation Units in Safety Train B Switchgear Room,In Response to NRC 790418 Request.Info to Be in Next Fire Hazard Analysis
ML19247B024
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 07/30/1979
From: Goodwin C
PORTLAND GENERAL ELECTRIC CO.
To: Schwencer A
Office of Nuclear Reactor Regulation
References
NPF-1, NUDOCS 7908060389
Download: ML19247B024 (6)


Text

_

r; : '.1 ^

'O [ci I

'55 Ek$

July 30, 1979

~

Trojan Nuclear Plant Docket 50-344 License NPF-1 Director of Nuclear Reactor Regulation ATTN:

Mr. A. Schwencer, Chief Opere. ting Reactors Branch #1 Division of Operating Reactors U.S. Nuclent Regulatory Commission

'4ashington, D. C. 20555

Dear Sir:

In accordance with our letter of June 19, 1979, we are providing the attached supplemental information justifying the heat removal adequacy of the air recirculation units in the Trojan Safety Train B Switchgear Room to remove energy generated by a potential fire. This information was originally requested in your Request for Additional Information of April 18, 1979. This information will be included in the next revision of the Trojan Nuclear Plant Fire Hazard Analysis, PCE-1012.

If you have any questions concerning this information, please contact me.

Sincerely, i[

C. Goodwin, Jr.

/

Assistant Vice President Thermal Plant Operation and Maintenance CC/SML/4sb7A16 At tac hment

$$gggp-L c:

Mr. Lynn Frank, Director w/ attach State of Oregon Departcent of E.tergy l /)

fi

  • C) 7908060l'87

ATTACHMENT 1 Request 3.2.2 Cable Tray Tests (Train B Switchgear Room)

The PGE letter of January 9, 1979 indicates that adequate test data is available in lieu of performing additional tests to obtain information related to switchgear room fire protection.

PGE in 1012 (Page C-50) indicates that the results of the test would be used in performing an analysis to show the adequacy of the air recirculation units in the gafety train B switch-gear room to remove the energy generated by a fire.

Identify when the results of this analysis will be provided using the available test data. This analysis should consider =aximum temperatures that train A equipment in this room can withstand without malfunction in addition to the maximum allowable cable temperature identified in PGE 1012, Pages C-49 and C-50.

Alternatives acceptable to the staff in lieu of performing this analysis are:

(a) Provide an alternate shutdown capability independent of cabling and equipment in this room to achieve safe shutdown, (b) Provide an automatic total flooding gas suppression system in this area, or (c) Install a 3-hr rated barrier to separate the train A cabling and equipment in the roca from the train B cabling and equipment.

Response

The safety train B switchgear room, located at El. 61 and 65 ft of the Control Building, contains the following train B switchgear:

4-kV switchgear (A2), 480-V motor control centers (B22, B24 and 526),

inverters (Y26 and Y28), battery chargers (D22 and D24), and the preferred instrument a-c buses (Y22 and Y24). It also contains the following train A switchgear:

inverters (Y15 and Y17), battery char-gers (D21 and D24), and the preferred instrument a-c buses (Yll and Y13).

All of the electrical equipment within this room was designed and manufactured to operate in a maxi =um ambient temperature of 104 F.

PGZ has performed a thermal analysis to show the adequacy of the air recirculation units in the safety train B switchgear rocm to remove the heat generated by a postulated fire. The analysis has been done for the most severe case of heat generation, due to a fire in the most concentrated cable tray arrangement. This arrangement is shown on the attached Sketch 1.

The arrangement of the air coolers with respect to the subject cable tray is shown on the attached Sketch 2.

It is judged that none of the air coolers would be affected by the postulated fire.

$U2

~

In order to conduct the thermal analysis, the following assumptions were made (the referenced reports were used as guide documents only):

1.

It takes 5 min after the fire source ignition for a fire to start in the bottom tray and then begin to vertically propagate to the next tray.

(Ref:

SAND 78-0518, Page 27 and SAND 77-1424, Page 15) 2.

The average rate of vertical cable flame spread was esti-mated to be 3 in./ min.

(Ref: Table 14 of NUREC/CR-0346) 3.

The average horizontal cable flame spread rate was assumed to be 1 in./ min, based on the Browns Ferry fire.

(Ref:

Brookhaven National Lab. Report, BNL-NUREC-23392, Page 5) 4.

During a cable fire, for the first 10 min, approximately 20 percent of the cable is consumed (BNL-NUREG-23392, Pages 6 and 7).

5.

Average initial room temperature was assumed to be 75*F.

6.

Combustible loading for each of the cable trays has been estimated to be 10.65 lb/ft.

7.

As stated on Page A-7 of the Trojan Fire Hazard Analysis, PCE-1012, a total heat release rate of 12,250 Btu /lba for the electrical cable insulation and jacketing (EPR) has been used in the analysis.

8.

The net heat load for the subject room due to the electrical equipment and lighting is approximately 277,700 Btu /hr.

9.

It has been established that each air recirculation unit could remove up to 250,000 Btu /hr in case of a postulated fire in the switchgear room.

10.

The worst-case cable tray configuration was considered burned.

11.

Five air recirculation units are operating.

Based on these assumptions, it was calculated that the switchgear room temperature will reach 104*F in approximately 21 =in and 180 F within 25 min (Sketch 3).

Other equipment operability scenarios were analyzed but were found to give similar conservative results.

It must be con-sidered that the detection system will alarm and responding operations personnel will be available and extinguishing a possible fire within minutes of fire initiation.

Also, upon actuation, the new smoke exhauster system will significantly reduce the switchgear rocs tem-perature. The air recirculation units are thus judged adequate to remove energy released by the postulated fire and thus preserve safe shutdown equipment and cable functionability.

b_682f;3 SML/4sb66.36321 BIA070 BBA070 h

s BBA611 BIA009 3BAl71 BBA0ll y

~

EM

% Q,.

BBA271

/'/'

~,.% ?. ~.'

5 El. 73'-5"

.- y f*

BBA189

~'

~

9" E1. 72'-8" s

8" El.

72'-0"

/

g, t','

9" El.

71'-3" 8" El.

70'-7" 12" 4",, " '

9" El. 69'-10" BIA011 ISOMETRIC OF CABLE TRAY SECTIONS III & VI ON DRAWING E-133 SWCR. "B" ROOM - CONTROL BUILDING EL.

61'-s" SKETCH NO. 1 568264

EOUIPMENT SOURCE SOURCE LOCATION V145A B21 EL. 69' TURB. BLDGi I"EMT ABI IOil UP TO V 14 5 B B22 EL. 61' CON TR. BLDG.

EL. 8 5' V 14 5C B23 EL. 69' TURB. BLOG.

/

V 14 5D B24 EL. 6 l' CONTR. BLDG.

H H

g g

t V 14SE B47 EL. 69' TU R B. BLDG.

V-14 5 A a

RIS E R FR O M E L. 7 0' 11" T O E L. 82' 6" (12")

M.

RISER FROM EL. 69'j0"

[8 A

'S I

T O EL. 8 7' 10" (24 )

g' B B A 013 H

x

, f p/

l" EMT B B 1010 g[{

h

'i.r, : t'

\\

v

[

Vl458 e

B AT T ER Y I.E E

UP i

BBAOO81 ROOM 0

./. /

~
.r-TRAIN B MCCB22 JBBA3ll r-BBIO48 C:

s,. ;

BBA611 B B A315 J

p " EMT ABilOI UP TO U ~T '1 BBA171 x

' s H

H c:

E L. 80, 0..

if.

w; BB AOli m N

BBA271

. c c. -

El T BAT T E RY Vl45C

.Lw.y F L. E L. 65'0" F L. E L. G l ' O" ROOM

',3 TR AIN A f/;

881029 s

.g c,

TRAYBBA801 CD gf b

FLOOR PLAN h

p MCCB24 CONTROL BUILDING EL. 61'-0" Cai WCH E R "B" ROOM I"

EMT N B 1 0 11 UP T O 1.. E M T B B il Ol E L. 8 8, 3,,

m TCH NO. 2 V 145 D Vl45E

==.

~

-U P H

'H H

r

TRAlti B SWITCilGEAR ROOM R00ft TEf1PERATURE DUE TO A" WORST CASE FIRE 180 --

(25,180)

Al.L 5 COOLERS IN OPERATION 170 150 o

iJ

$ 110 tYs W

l10 -

(21,104)

'J U

(.C (f.

SKETCil No. 3 CD N

CS C

70 0

10 20 30 TI!1E, f1IN TROJAN NUCLEAR PLAflT

.