UNITED STATES E \\ 3.,(h NUCLEAR REGULATORY COMMISSION Di. ' '
'/, c REGION IV 0,
[
611 RYAN PLAZA DRIVE, SUITE 1000 o-AR Lib'iToN, TiEX AS 76012
.+
c June 5, 1979 Docket Number 99900521
^
Bechtel Power Corporation Los Angeles Power Division Atta:
Mr. I. R. Caraco Vice President and General Manager Post Office Box 60860 Terminal Annex Los Angeles, California 90060 Gentlemen:
A series of Nuclear Regulatory Commission (NRC) inspections have been conducted to review your implementation of the Quality Assurance Program applicable to NRC applicants or licensees who have contracted for services from the Los Angeles Power Division of the Bechtel Power Corporation.
These inspections consisted of selective examination of procedures and representative records, interviews of personnel and direct observation by the inspectors.
As a result of these inspec-tions, the NRC Office of Inspection and Enforcement (IE) has concluded that the QA program described in Topical Report B,-TOP-1, Revision 2A, is being implemented satisfactorily.
Neither this conclusion nor the remainder of this.'.etter applies to any activities conducted at reactor sites.
Licensees and applicants that have referenced the above Topical Report in their Safety Analysis Reports (or have adopted the total quality assurance program described in that Topical Report) may at their option use this letter to fulfill their obligation under 10 CFR Part 50, Appendix B, Criterion VII, that requires them to perform initial source evaluation / selection audits and subsequent periodic audits to assess the quality assurance program implementation.
The NRC expression of satisfaction with the implementation of ysur QA program does not assure that a specific product or service offered by you to your customer is of acceptable quality, nor does it relieve the applicant or licensee from the general provision of Criterion VII which requires verification tnat purchased material equipment or services conform to the procurement documents.
It is recognized that in some cases *his assurance can be made by the applicant or licensee without audits or inspections at your facility.
kkb 2908020 @
A Bechtel Power Corporation June 5, 1979 Los Angeles Power Division Continuing acceptability of implement 2 tion of your QA program is contingent upon.
your maintaining a satisf actory le el of program implemencation, verified through periodic IE inspection, throughout all corporate organization units and nuclear projects encompassed by your program.
Should your program implementation at any time be found unacceptable you will be notified by letter, and requested to correct the deficiencies promptly.
In the event you fail to correct the deficiencies promptly, or if the record of defi-ciencies is such as to indicate generally poor program implementation, you and the applicants and licensees who have referenced your QA program will be notified that the generic imple=entation of your program is no longer acceptable to the NRC.
All of the audit /Jnspection requirements of Criterion VII, Appendix B, 10 CFR 50, ettst then be implemented by the applicants or licensees.
The NRC will reinstate its letter of acceptability of implementation of yi2r QA program only after our inspectors have concluded, based on reinspection, that you have again demonstrated full compliance.
Except as noted above, the conclusions expressed in this letter will be effective for three years from the date of issue of the letter.
At this time program perform-ance over the previous three year period will be evaluated and this letter reissued, if appropriate.
The results of our inspections are published quarterly in the Licensee, Contractor and Vendor Inspection Status Report (NUREG 0040), which is made available to NRC facility applicants, licensees, contractors and vendors, as well as to members of the public.
Sincerely, 9)
Ka'l V. Seyfrit Director iO i