SUMMARY
OF ACTIVITIES AT TMI FOR GREGORY C. SMITH k>
]
l.
Time of Arrival:
0700 hrs., 5/18/79 Time on Duty:
0700 hrs. to 1600 hrs., 5/18-19/79 0700 hrs. to 1900 hrs., 5/20/79 0700 hrs, to 1600 hrs., S/21-24/79 0700 hrs. to 1400 brs., 5/25/79 Total:
72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> 2.
Summary of Activities While on duty, I was a member of the Environmental Mohile Survey Team.
Specific activities included taking air samples at various off-site locations as determined by meteorologic data, taking vegetation samples, and performing direct radiation surveys of the environment.
3.
Due to the nature of the work activities, my contact with the licensee was minimal. Therefore, I have no comments regarding licensee operations.
4.
No comment.