Summary of 790611-13 Visit to B&W Lynchburg,Va Research Ctr
ML19242B282
Person / Time
Site: 07000824
Issue date: 07/02/1979
From: Ketzlach N
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
To: Crow W
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
References
NUDOCS 7908070818
Download: ML19242B282 (2)


Text

.

I f "E%

R UNITED STATES

$\\

$. " {,{-f(((/s* &a*p,E 7,

NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 zi r

g

' ((;j

  • a f1EMCRAtiDU 1 FOR:

W. T. Crow, Section Leader Uranium Fuel Fabrication Section Fuel Processing & Fabrication Branch Division of Fuel Cycle and Material Safety FROM:

florman Ketzlach Uranium Fuel Fabrication Section Fuel Processing & Fabrication Branch Division of Fuel Cycle and flaterial Safety

SUBJECT:

TRIP REPORT Purpose Visit licensee's facilities and discuss the S:iM-778 license renewal application of the Babcock and Wilcox Lynchburg Research Center (LRC).

Place and Date Lynchburg Research Cer.ter, Lynchburg, Virginia, June 11-13, i979.

Attendees Lynchburp Research Center -

A. F. Olsen, License Administrator F. it. Alcorn, fluclear Safety Officer J. W. Cure, Suprrvisor health and Safety J. P. Doran, Manager Accounting and Administrative Services U.S. fluclear Regulatory Commission -

it. Ketzlach, NilSS A. L. Soong, flMSS J. B. Kahle, ISE Region II Discussion fl. Ketzlach, A. L. Soong, and J. B. Kahle toured the facilities of the Lynchburg Research Center with A. F. Olsen.

During the tour a building housing SNM wastes (Building J) was seen that was not discussed in the renewal application.

J. B. Kahle identified several items that should be incorporated in the license to clarify its application.

These items will be incorporated in the formal cornments to be submitted to the LrtC on thcir renewal application.

S0b I

908 070f/6

2 Discussions were held on the fiRC preliminary comments associated with radiation safety, nuclear criticality safety, process safety, fire protection and the emergency plans. All attendees, excluding Mr. Doran, participated in all the dis 2ssions. The latter participated only in the discussion of the emerge. icy plan.

The LRC personnel have an understanding how they will develop the response to the NRC comments associated with nuclear criticality and process safety and the emergency plan.

However, they feel additional time will be required for them to determine their respcnse to some of the comments associated with radiation safety and fire protection.

In order to meet the radiation safety requirements for the facility air monitoring program and respond to the NRC comments associated wich the bioassay program and with ALARA, they feel further evaluation of their methods for radiation protection is necessary. Therefore, the LRC stated they could not meet the NRC " Gold Book" schedule of August 3, 1979, for response to our comments.

However, they agreed to submit their response by September 10, 1979.

The biggest p.oblem in the fire protecticn area is the use of polyethylene pipe in the ductwork associated with the B0G box off gas system for the glove boxe>) in Building C.

D. Notley Engineering Methodology Standcrds Branch) who is performing the fire safety review of the renewal application, will evaluate the use af the polyethylene piping during his site visit te be made in the nea future.

Prior to departure, N. Ket7.lach, A. L. Soong and J. B. Ka!..e met with A.

F. Olsen and Dr. E. D. Lynch, Manager b terials and Chemical Technology Laboratory, (acting for the Director of the Lynchburg Research Center) to discuss the meeting summary.

Conclusions The site visit and discussion of the NRC preliminary comments should expedite the reviaw of the LRC renewal application. The LRC has determined that they must make an additional study of its operations before they can respond to the NRC comments.

They have agreed to submit tneir response by September 10, 1979.

l j

/

/

og gg

.A Norman Kttzloch Uranium Fuel Fabricatic Fuel Processing & Fabrit

. ich Division of fuel Cycle m.

Material Safety Approved by:

/

/

W. T. Crow, Section Leader 4

l s h