Category:Meeting Summary
MONTHYEARML23313A1172023-11-21021 November 2023 October 26, 2023 Summary of Holtec International Pre-decisional Enforcement Conference ML23097A1162023-04-0505 April 2023 Enclosusummary of Discussion 04-05-2023 ML23058A1232023-02-22022 February 2023 Enclosusummary of Phone Call with Holtec International (Holtec) on 02-22-2023 Shielding Topical Report ML22297A1272022-10-31031 October 2022 Summary of Meeting with Holtec International to Discuss Clarification of Holtec'S Responses to Request for Additional Information for the Shielding Topical Report ML22297A1252022-10-31031 October 2022 Enclosure 1 - Summary of RAI Discussion Between NRC and Holtec Staff ML22207B7842022-08-0101 August 2022 Memo Meeting Summary for CoC No. 1014, Amendment No. 18 - Rsi Clarifications ML21326A0812021-11-30030 November 2021 November 10, 2021, Summary of Public Meeting with Holtec International to Discuss Pre-Application of Certificate of Compliance No. 1014, Amendment No. 18 ML21237A0432021-08-25025 August 2021 Summary of July 27, 2021, Public Meeting with Holtec International to Discuss Certificate of Compliance No. 1014 for the HI-STORM 100, Amendment No. 16, Graded Approach ML21082A0852021-04-0909 April 2021 Summary of Closed Meeting with Holtec International and U.S. Nuclear Regulatory Commission Regarding Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems ML20064F6162020-02-29029 February 2020 January 15, 2020, Summary of Meeting with Holtec International, Inc., to Discuss the Upcoming Submittal of the Application for Renewal of the Storage Certificate of Compliance No. 1014 for the HI-Storm 100 Cask System ML19241A2762019-08-29029 August 2019 Memorandum to C. Regan Summary of August 19, 2019, Partially Closed Public Meeting with Holtec International to Discuss Pre-Application of Thermal Topical Report (W/Enclosure) ML18289A4132018-10-16016 October 2018 Memorandum to A. Rivera-Varona Summary of September 12, 2018, Licensing Meeting with Holtec International to Discuss Technical Topics Related to Two Amendments Applications (W/Enclosure) ML18254A0762018-09-11011 September 2018 Public Meeting Summary: Meeting Handouts for Amendment No. 13 to Certificate of Compliance No. 1014 for the HI-STORE 100 Multi-Purpose Canister Storage System Docket No. 72-1014: Summary of Technical Issues ML13119A5812008-04-0909 April 2008 April 9, 2008, Conference Call Summary Hydrogen Event at CSG 2023-04-05
[Table view] Category:Memoranda
MONTHYEARML24018A0852024-01-31031 January 2024 Safety Determination of a Potential Structural Failure of the Full Basket During Accident Conditions for the HI-STORM 100 and HI-STORM Flood/Wind Dry Cask Storage Systems ML23123A1032023-12-20020 December 2023 User Need for Rulemaking for the Holtec HI-STORM 100 Cask System, Amendment No. 16 ML23313A1172023-11-21021 November 2023 October 26, 2023 Summary of Holtec International Pre-decisional Enforcement Conference ML22313A0382022-12-19019 December 2022 Corrected User Need for Rulemaking for Amendment No. 17 to HI-STORM 100 System ML22297A1272022-10-31031 October 2022 Summary of Meeting with Holtec International to Discuss Clarification of Holtec'S Responses to Request for Additional Information for the Shielding Topical Report ML22175A0872022-08-24024 August 2022 Preliminary HI-STORM 100 Amendment 17 User Need Memo ML22207B7842022-08-0101 August 2022 Memo Meeting Summary for CoC No. 1014, Amendment No. 18 - Rsi Clarifications ML22098A2342022-04-14014 April 2022 User Need Memo for Renewal of CoC No. 1014 (HI-STORM 100 Cask System) ML21326A0812021-11-30030 November 2021 November 10, 2021, Summary of Public Meeting with Holtec International to Discuss Pre-Application of Certificate of Compliance No. 1014, Amendment No. 18 ML21237A0432021-08-25025 August 2021 Summary of July 27, 2021, Public Meeting with Holtec International to Discuss Certificate of Compliance No. 1014 for the HI-STORM 100, Amendment No. 16, Graded Approach ML21082A0852021-04-0909 April 2021 Summary of Closed Meeting with Holtec International and U.S. Nuclear Regulatory Commission Regarding Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems ML21077A2682021-03-22022 March 2021 Summary of March 10, 2021, Public Meeting with Holtec International to Discuss Pre-Application of Shielding Method of Evaluation Topical Report ML20295A4132021-01-27027 January 2021 User Need for Rulemaking for the Holtec HI-STORM 100 Cask System, Amendment No. 15 ML20064F6162020-02-29029 February 2020 January 15, 2020, Summary of Meeting with Holtec International, Inc., to Discuss the Upcoming Submittal of the Application for Renewal of the Storage Certificate of Compliance No. 1014 for the HI-Storm 100 Cask System ML19330E4052019-12-0404 December 2019 Holtec Thermal Topical Report Pre-application Meeting #2 Summary ML19241A2762019-08-29029 August 2019 Memorandum to C. Regan Summary of August 19, 2019, Partially Closed Public Meeting with Holtec International to Discuss Pre-Application of Thermal Topical Report (W/Enclosure) ML19120A0572019-07-0909 July 2019 Memorandum to J. Cai User Need for Rulemaking for the Holtec HI-STORM 100 Cask System, Amendment No. 14 ML19071A2942019-03-12012 March 2019 Regulatory History for CoC 1014 Amendment Nos. 11 and 12 ML19024A0502019-01-24024 January 2019 Summary of Partially Closed Pre-Application Meeting with Holtec International to Discuss Proposed Amendment Application to CoC No. 1014 for HI-STORM 100 Multipurpose Canister Storage System (W/Encl. 1) ML18351A1722019-01-17017 January 2019 Memorandum to K. Morgan-Butler User Need for Rulemaking for Amendment No. 13 to the Holtec International HI-STORE 100 Cask System ML18306A7682018-11-0101 November 2018 Memorandum to Y. Diaz-Sanabria Summary of October 17, 2018, Partially Closed Pre-Application Meeting with Holtec International to Discuss Proposed Amendment Application to Certificate of Compliance No. 1014 for HI-STORM 100 (W/Enclosure 1) ML18289A4132018-10-16016 October 2018 Memorandum to A. Rivera-Varona Summary of September 12, 2018, Licensing Meeting with Holtec International to Discuss Technical Topics Related to Two Amendments Applications (W/Enclosure) ML18087A0562018-05-25025 May 2018 Memorandum to K. Morgan-Butler User Need for Rulemaking for the Holtec Hi-Storm 100 Cask System, Amendment No. 12 ML17143A1552017-06-0606 June 2017 Memorandum to C. Bladey Notice of Availability of Exemption for Entergy Energy Operations, Inc., Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation ML17045A5282017-05-25025 May 2017 Memo to C. Bladey Notice of Availability of Environmental Assessment and Finding of No Significant Impact for Entergy Nuclear Operations, Inc., Vermont Yankee Nuclear Power Station, Independent Spent Fuel Storage Installation Exemption Requ ML14351A2602014-12-19019 December 2014 Memo C K Bladey Re Notice of Issuance of Exemption from Holtec Intl CoC No. 1014 Fuel Specification and Loading Conditions at Arkansas Nuclear One ISFSI ML14345B0652014-12-11011 December 2014 Memo C Bladey Re Federal Register Notice of Issuance of Environmental Assessment and Finding of No Significant Impact ANO Units 1 & 2 ISFSI 72-12 and 72-1014 ML0726300142007-09-26026 September 2007 L. Reyes Memo Direct Final Rule - HI-STORM 100, Amend 4 - EDO Pkg. - to Amend 10 CFR Part 72 List of Approved Spent Fuel Storage Casks ML0215803662002-06-0606 June 2002 Memo to R. Bellamy, RGN-I from: M. Tokar Subject: Region I Independent Spent Fuel Storage Installation Inspection Plans Attachment: Sfpo Comments to Region I Integrated Inspection Plans 2024-01-31
[Table view] |
Text
August 29, 2019 MEMORANDUM TO: Christopher M. Regan, Deputy Director Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards FROM: Christian Jacobs, Sr. Project Manager /RA/
Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards
SUBJECT:
SUMMARY
OF AUGUST 19, 2019, PARTIALLY CLOSED PUBLIC MEETING WITH HOLTEC INTERNATIONAL TO DISCUSS PRE-APPLICATION OF THERMAL TOPICAL REPORT On August 19, 2019, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and Holtec International (Holtec, the applicant). The purpose of the meeting was to discuss Holtecs plans for submittal of a Thermal Topical Report for allowance of candidate heat load patterns without an amendment request. The meeting notice and agenda, dated July 31, 2019, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML19212A763. During the meeting, the applicant presented slides, which are available at ADAMS Accession No. ML19212A455. The enclosure to this document contains the meeting attendance list.
After introductions, NRC managment made the following opening remarks: 1) Topical Reports are common in other parts of the agency, but they are not typical in the Division of Spent Fuel Management, 2) the Topical Report is not a substitute or replacement for the required licensing action (e.g, amendment, exemption, etc.), 3) there will be a need to discuss further how the Topical Report would be incorporated.
The applicant discussed how they plan to propose a suitable methodology permitting licensee qualification of candidate heat load patterns without the need for a license or Certificate of Compliance amendment. It is the applicants intent that the Topical Report would receive NRC approval, and that the approved methodology would allow Holtec, and its clients, to address emerging plant needs in a timely manner. Holtec stated that an approved Topical Report would prevent future undue engagement of regulatory resources by requiring fewer amendment submissions, and that some previous amendment applications would have essentially not been needed if the approved methodology was already in place.
CONTACT: Christian Jacobs, NMSS/DSFM 301-415-6825
C. Regan Most of the discussions were associated with questions (Q) from NRC staff and the public.
Holtec attempted to answer (A) as many of these questions as possible. However, Holtec stated that the details of this application were still being worked out internally. Some of the key Q&As regarding this pre-application are discussed below:
- Q: NRC staff asked when the Topical Report would be submitted? A: Holtec stated, early next year, maybe within the next 6 months.
- Q: NRC staff and the public asked how the Topical Report will address concerns regarding the effects of decay heat on other disciplines? The scope of the Topical Report was unclear. A: Holtec stated that they intend to stop referring to this application as a Thermal Topical Report and more simply state it as a Topical Report, because they do plan to address the effects on other disciplines such as shielding, criticality, structural, etc.
- Q: NRC staff and the public asked questions trying to understand the parameters of the Topical Report (e.g., limits on heat load, bounding parameters, etc.)? There were concerns that the Topical Report appeared to be opened ended, and it was not clear if the Topical Report would place any limits on total heat load or a per assembly basis.
A: Holtec stated that these details had not been fully worked out yet, but that some limit/bounds will be proposed.
- Q: NRC staff asked if the Topical Report would be submitted separately or as part of an amendment? A: Holtec indicated that the Topical Report would be submitted separately, and if approved, then Holtec would submit a separate amendment request at some future date to incorporate the Topical Report.
- Q: NRC staff was not clear on which regulations Holtec is trying to meet with this Topical Report? A: Holtec indicated they would provide those details in the application.
No regulatory decisions were made during the meeting. Several members of the public attended the meeting and asked questions. Some of the publics questions were similar in nature to NRC staffs questions reqarding the envelope or boundaries of the Topical Report.
There were also some additional concerns (e.g., transportation, retrievability, consolidated interim storage applications) raised by the public that were out of scope for this meeting.
Holtec is planning to request another pre-application meeting prior to their official submittal.
Holtec indicated they may try to schedule the next meeting with the NRC before the end of calendar year 2019.
Docket No.: 72-1014
Enclosure:
List of Attendees
C. Regan
SUBJECT:
SUMMARY
OF AUGUST 19, 2019, PARTIALLY CLOSED PUBLIC MEETING WITH HOLTEC INTERNATIONAL TO DISCUSS PRE-APPLICATION OF THERMAL TOPICAL REPORT, DOCUMENT DATE: August 29, 2019 DISTRIBUTION: (EPID L-2019-LRM-0044)
DSFM r/f DMarcano NRC Attendees G:\SFST\Jacobs\Holtec Thermal Topical Report\Pre-Application Meeting\Meeting Summary ADAMS Package No. ML19241A275 Memo: ML19241A276 Slides: ML19212A455 Meeting Notice: ML19212A763 OFFICE: DSFM DSFM DSFM NAME: CJacobs SFigueroa (via email) JMcKirgan DATE: 8/28/19 8/28/19 08/29/19 OFFICIAL RECORD COPY
LIST OF ATTENDEES SELF IDENTIFIED AUGUST 19, 2019, PUBLIC MEETING REGARDING PRE-APPLICATION OF HOLTECS THERMAL TOPICAL REPORT Name Affiliation Christian Jacobs U.S. Nuclear Regulatory Commission (NRC)
John McKirgan NRC Jason Piotter NRC Yoira Diaz Sanabria NRC Tae Ahn NRC JoAnn Ireland NRC Tim McCartin NRC Joe Borowsky NRC Jimmy Chang NRC Chris Bajwa NRC Meraj Rahimi NRC Christian Araguas NRC Jorge Solis NRC Caylee Kenny NRC (by phone)
Tony Rigato NRC (by phone)
Alexis Sotomayor Rivera NRC (by phone)
Kimberly Manzione Holtec International (Holtec)
Abrar Mohammad Holtec Debabrata Mitra-Majumdar Holtec Stefan Anton Holtec (by phone)
Indresh Rampall Holtec (by phone)
Donna Gilmore Member of the public Marvin Resnikof Member of the public Enclosure