Enclosure NRC Critical Path Schedule of Potential Licensing Actions related to ATF with Increased Enrichment (<10%)
Note: All durations for industrys activities are estimated. Start to Finish dates were selected using industrys published goal for ATF deployment (2023 - fall reactor outage) and going backwards for the steps needed to support deployment date.
Start 08/06/21 Finish 11/29/23 Sep '21 Oct '21 Nov '21 Dec '21 Jan '22 Feb '22 Mar '22 Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Aug '23 Sep '23 Oct '23 Nov '23 Enrichment Facility -
Plant Modifications 08/06/22 - 12/04/22 NRC Review - CoC Revision - UF6 Transportation Package 08/06/21 - 02/02/23 Fuel Fab Facility - New Fuel Manufacturing 04/18/23 - 08/16/23 NRC Review - CoC - Fresh Fuel Transportation 02/17/22 - 08/16/23 NRC Review - Enrichment Facility - License Amendment 08/06/21 - 08/06/22 Enrichment Facility -
Enrich Material 12/04/22 - 02/02/23 UF6 Transport ation 02/02/23 03/04/23 Fuel Fabrication Facility License Amendment 10/20/21 - 10/20/22 Fuel Fab Facility - Plant Modifications 10/20/22 - 04/18/23 Enriched UF6 Receipt and Inspection 03/04/23 -
04/18/23 Fresh Fuel Transportation to Reactor 08/16/23 - 09/15/23 Reactor -
Enriched Fuel Receipt and Inspection 09/15/23 Reactor -
Batch Load Enriched Fuel Industry goal -
Batch Load 2023 11/29/23