NRR E-mail Capture - 08/21/2019 Public Meeting with the Nuclear Energy Institute to Discuss the Use of New Probabilistic Risk Assessment Methods Following the Issuance of an Amendment to Utilize a Risk-Informed Process - Slides - IP Revisio
ML19231A470
Person / Time
Issue date: 08/16/2019
From: Antonios Zoulis
NRC/NRR/DRA
To: Ed Miller
Special Projects and Process Branch
References
Download: ML19231A470 (6)


Text

NRR-DRMAPEm Resource From: Zoulis, Antonios Sent: Friday, August 16, 2019 3:50 PM To: Miller, Ed Cc: Weerakkody, Sunil

Subject:

IP Revisions(August 2019).pptx Attachments: IP Revisions(August 2019).pptx Ed, Attached are my slides for the August 21, 2019 public meeting.

Antonios 1

Hearing Identifier: NRR_DRMA Email Number: 181 Mail Envelope Properties (BN7PR09MB26923F0017BFD95B1F5E707CE2AF0)

Subject:

IP Revisions(August 2019).pptx Sent Date: 8/16/2019 3:50:05 PM Received Date: 8/16/2019 3:50:08 PM From: Zoulis, Antonios Created By: Antonios.Zoulis@nrc.gov Recipients:

"Weerakkody, Sunil" <Sunil.Weerakkody@nrc.gov>

Tracking Status: None "Miller, Ed" <Ed.Miller@nrc.gov>

Tracking Status: None Post Office: BN7PR09MB2692.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 93 8/16/2019 3:50:08 PM IP Revisions(August 2019).pptx 2221305 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

Inspection of Risk-Informed Initiatives Antonios M. Zoulis, Branch Chief PRA Oversight Branch Division of Risk Assessment Office of Nuclear Reactor Regulation August 21, 2019

Risk-informed Inspection Procedure Changes

  • Guidance to inspectors when conducting Reactor Oversight Process baseline inspections of 10 CFR 50.65 (maintenance rule), 10 CFR 50.69 (risk-informed categorization and treatment of equipment),

and risk-informed Technical Specification initiatives such as Risk-Informed Completion Times (4B) & Surveillance Frequency Control Programs (5B).

  • Intended to provide a better understanding of the regulatory framework, as well as focus inspector efforts.
  • Inspection procedure sample size and level of effort remains the same.
  • Intent is for the Inspection Procedures to be finalized and in place by January 1, 2020.

2

Risk-informed Inspection Procedure Changes (Cont.)

Draft IPs: ADAMS Package No. ML19197A293

- 10 CFR 50.69 / aging management / new format

  • IP 71111.13, Maintenance Risk Assessments and Emergent Work Control

- Risk Informed Completion Times (RICTs)

- 10 CFR 50.69 / TS Surveillance Frequency Control Program / RICTs

- TS Surveillance Frequency Control Program

- 10 CFR 50.69 3

Questions?