UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of TENNESSEE VALLEY AUTHORITY (Clinch River Nuclear Site Early Site Permit Application)
Docket No. 52-047-ESP Hearing Exhibit Exhibit Number:
Exhibit
Title:
United States Nuclear Regulatory Commission Official Hearing Exhibit In the Matter of:
TENNESSEE VALLEY AUTHORITY (Clinch River Nuclear Site Early Site Permit Application)
Commission Mandatory Hearing Docket #: 05200047 Exhibit #:
Identified:
Admitted:
Withdrawn:
Rejected:
Stricken:
Other:
TVA-009-MA-CM01 8/14/2019 8/14/2019 TVA-009 Curriculum Vitae of John Holcomb
John Holcomb Tennessee Valley Authority 1101 Market St. Chattanooga, TN 37402 (423) 751-3743 jmholcomb@tva.gov EDUCATION Bachelor of Science in Civil Engineering, 2009, Auburn University EXPERIENCE 2010 to present - Tennessee Valley Authority o Engineering Manager, Nuclear Technology Innovation (2016-Present)
Responsible for managing employees, contractors, and vendors to perform engineering work in support of SMRs at the Clinch River Site and other nuclear technology innovation projects.
o Project Manager, Nuclear Projects (2014-2015)
Responsible for multiple technical projects in the areas of FLEX, seismic probabilistic risk assessments, EPA 316b environmental regulations and emergent nuclear fleet issues.
o Senior Systems Engineer, Watts Bar Nuclear Plant (2013-2014)
Performed engineering technical evaluations and provided support for outages, modifications, inspections and testing.
o Civil Engineer, Bellefonte Nuclear Plant (2010-2013)
Performed civil engineering and construction planning activities in support of the planned nuclear plant construction.