ML19225D323
| ML19225D323 | |
| Person / Time | |
|---|---|
| Site: | Callaway |
| Issue date: | 08/12/2019 |
| From: | Ameren Missouri, Union Electric Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML19225D321 | List: |
| References | |
| ULNRC-06524 | |
| Download: ML19225D323 (1) | |
Text
Attachment 1 to ULNRC-06524 Page 1 of 1 LIST Of REGULATORY COMMITMENTS The following table identifies those actions identified as regulatory commitments by Ameren Missouri in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments. Please direct questions regarding these commitments to Bruce Huhman at (573) 694-6741.
Regulatory Commitments and Completion Schedule Modification Completion Date Commitment Tracking Number Install Anchorage to the Alternate Emergency December 3 1, 2020 50431 Power Supply transformer (XPBO5).
Provide a minimum of 1-inch clearance around December 3 1, 2020 50432 two fire sprinkler heads located on the 1974 elevation of the control building at grid C4 &
CC,andgridC2&CB.
$315 County Road 459 Steedman, MO 65077 AmerenMissourLcom