ML19225B559

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-440/79-04 & 50-441/79-04 on 790418-20. Noncompliance Noted:Improper Storage of Pipe Sleeves
ML19225B559
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 05/15/1979
From: Julie Hughes, Knop R, Konklin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19225B556 List:
References
50-440-79-04, 50-440-79-4, 50-441-79-04, 50-441-79-4, NUDOCS 7907250452
Download: ML19225B559 (9)


See also: IR 05000440/1979004

Text

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-440/79-04; 50-441/79-04

Docket No. 50-440; 50-441

License No. CPPR-148; CPPR-149

Licensee: The Cleveland Electric Illuminating

Company

Post Office Box 5000

Cleveland, OH 44101

Facility Name:

Perry Nuclear Power riant, Units 1 and 2

Inspection At:

Perry Site, Perry, OH

Inspectfan Conducted:

April 18 - 20, 19'9

Inspecters:

J. E. Konkl4[ ,

NS'/77

/

/

/S

f

u

.

'

_3

,

(..

pa c. / e L '

_,

'

Approved y:

R. 6. Knop,,Snief

O // 3 / 7f

'

'

Projects Section

_ Inspection Summary

Inspection on April 18 - 20, 1979 (Report No. 50-440/79-04 and 50-441/79-0_4)

Areas Inspected:

Ongoing site construction activities (Units 1 and 2);

licensee actions relative to previous unresolved items and items of noncor

_

pliance; licensee actions relative to handling of IE Bulletins and IE

Circulars; implementing procedures for electrical components and systems

(Units 1 and 2); implementing procedures for electrical cables and

terminations (Units 1 and 2); work activities related to electrical

components and systems (Unit 1).

The inspection involved a total of 40

onsite inspector-hours by two NRC inspectors.

Results: Of the six areas inspected, one item of noncompliance was

identified in one area (infraction - improper storage of pipe sleeves -

Section I, Paragraph 3).

411

351

2 90'n504 R

.

DETAILS

Persons Contacted

Principal Licensee Employees

  • M. R. Edelman, Manager, Nuclear QA Department

G. W. Groscup, Fbnager, Nuclear Engineering Department

  • D.

A. Fitzpatrick, Site Construction Manager

  • W.

J. Kacer, CQS General Supervising Engineer

  • P.

Martin, Program QA General Supervisor

  • H.

Balvin, Licensing and Administration Planning Engineer

  • R.

Pointer, Licensing Engineer

  • J.

Pepp, CQS Senior St.cretary

Other Personnel

  • P. L. Gibson, CQS Quality Control Supervisor (KEI)
  • G. J. Gibson, CQS Acting Quality Engineering supervisor (GAI)
  • D. Cooper, CQS Quality Administration Supervisor (KEI)

J. W. Mehaffey, CQS Lead Mechanical Quality Engineer (G AI)

R. E. Crofton, CQS Lead r_ning Quality Engineer (GAI)

W.

Ware, CQS Civil Quality Engineer (GAI)

The inspectors alse contacted other licensee and contractor employees,

including members of the quality, technical and engineering staffs.

  • Denotes those who attended the exit interview.

Licensee Action on Previous Inspection Findings

(Closed) L'nresolved Item (440/77-04; 441/77-04):

Placement of heavy-

weight concrete.

Previous RIII Reports (440/77-04; 441/77-04) and

(440/77-U6; 441/77-06) questioned specific aspects of the use of

iron oxide mortar in the biological shield wall.

Subsequent corre-

spondence between the licensee and RIII 7 arrowed tne areas in

question down to whether the weight and thermal conductivitiy of the

heavyweight concrete had been taken into consideration in the plant

design analyses. During this inspection, the inspector reviewed,

and discussed with the licensee, supplemental engineering work si.eets

which showed that GAI had incorporated the heavyweight concrete design

parameters into the appropriate seismic, dead weight, and thermal

analyses.

This item is considered to be resolved.

(Closed) Noncompliance (440/78-02-14; 441/78-01-14):

Failitre to docu-

ment and identify voids on concrete placement.

The previous RIII

report (440/78-02; 441/78-01) noted that National Engineering failed

-2-

411

352

.

'

to docuo.ent voids on a concrete placement in the Intermediate Building

on a Nonconformance Report (NR), or to identify the specific void areas

with a nonconformance tag or other means.

During this inspection,

the inspector inspected National Engineering concrete placement areas

in the Intermediate Building, and found no examples of unacceptable

volds which were not identified.

The inspector also selected one

specific area with voids at the 620 ft. level of the Intermediate

Building and reviewed the applicable Nonconformance Report, NR 447,

dated February 28, 1979.

NR 447 showed that the void area had been

properly identified and placed on hold pending chipout and further

evaluation. This item ir closed.

.

411

353

- 3-

.

Secticn I

Prepared by J. E. Konklin

Reviewed by R. C. Knop, Chief

Proj ects Section

1.

Review of Licensee Actions on Previous Inspection Findings

The RIII inspector reviewed the licensee's actions relative to

the resolution of soecific inspection findings which were identi-

fied in previous RIII inspection reports, and which were still

in an open status prior to this inspection.

The items reviewed,

and the licensee actions relative to the resolution of the items

are discussed in the foregoing section of this report.

2.

Review of Licensee Actions Relative to IE Bulletins and Circulars

The Region III inspector reviewed the licensee's handling of

IE Bulletins and Circulars to determint whether an effective

system has been set up for evaluating and responding to the

Il documents, and whether the system has been effectively

implemented.

Included in the review were discussions with CEI

CQS and Licensing personnel, and review of the following documents:

a.

CEI Nuclear Design Instruction 35-0603, Revision 0, effective

January 18, 1979, " Coordination of Responses to NRC IE

Bulletins and Circulars."

b.

The CEI IE Bulletin Log, which contains copies of all bulletins

sent to CEI, and related correspondence, from Bulletins 77-01

.

through 79-03A.

c.

The CEI IE Circular Log, which contains copies of all circulars

sent to CEI, and related correspondence, fron Circulars

76-01 through 79-07.

The review indicated that, although Instruction 35-0603 was not

effective until January 18, 1979, it served primarily as a written

formalization of the practices wh3ch had been followed by CEI

previously in the evaluation of and response to bulletins and

circulars.

The inspector reviewed the documentation for all of the bulletins

and circulars logged by CEI to determine whether distribution was

made to the appropriate persons, whether the required evaluations

411

354

-'-

.

were performed, whether timely tesponses were sent to NRC, ar.i

whether the responses addressed the appropriate technical

questions.

The inspectors then c;1ected six specific bulletins

and one circular, which were considered to be of particular

significance, and performed a more detailed review of the evalu

ations and responses for those specific items.

The results

of the detailed reviews are discussed in Section II of this re' ort.

Of the 22 IF Bulletins issued during 1977 and 1978, ten bul1< tins

wer e either not applicable to the Perry Project or did not require

an answer. One bulletin (78-12), which has not yet been answered,

has received extensions in response time (per 78-12a and 78-12b)

to May 29, 1979.

The responses for ti:e remaining 11 bulletins

-ere considered to be adequate. With regard to IE Circulars,

a total of forty were issued during 1976, 1977 and 1978, with an

additional five issued in 1979 through March 20, 1979

Of the

45, 12 were not applicable to Ferry, and only four of the others,

all in 1976, required responses. The licensee'n re ords indicate

adequate consideration of IE Circulars.

Based on the review, the RIII inspector concluded that:

a.

CEI has implemented an effective system for the handling

of IE Bulletins and Circulars;

b.

The evaluation of and response to bulletins and circulars

has been perf ormed in a systematic and timely manner;

c.

For those bulletins selected and reviewed in more detail,

the technical evaluation performed by the licensee appears

to be adequate (see Section II).

All IE Bulletins issued during 1977 and 1978, except for 78-12

(inclo?ing 78-12a and 78-12b), are considered to have been adequately

evalutted snd responded to by CEI; all IE Circulars issued during

1976, 1977, 1978, and through 79-05 in 1979 are considered to

have teceived adequate consideration by CEI althcugh, as noted

is. Set'. ton II of this report, additional RIII inspections will be

made wiC regard to Circular 78-08.

3.

Ongoing Cens.ruction Activities

The inspector observed ongoing work activities and equipment

status in the Units 1 and 2 containment buildings, including

the Unit I reactor pedestal area, the Units 1 and 2 auxiliary

buildings, the intermediate building, the control complex, and

the fuel handling building.

411

355

- s-

On April 20, 1979, at azimuth 210 vu the Containment No. I weir

mat level, the inspector observed ten 36-inch diameter pipe

sleeves for the bioshield which were improperly stored, in that

the sleeves were not on dunnage, and there were ladders, chunks

of steel, and angle iron lying on the sleeves.

The inspector

reviewed the applicable Newport News specification, SP-96-4549-00

dated December 18, 1975, and found that Section 5:16 " Receiving,

Storage, and Handling," requires storage of the sleeves to be

in accordance with ANSI N45.2.2 Level D.

The inspector notified

the licensee that the storage of the sleeves, which does not

comply with the requirements of ANSI N45.2.2 Level D,

is also

in noncompliance with Criterion XIII of 10 CFR 50, Appendix B.

(440/79-04-01; 441/79-04-01)

Except for the item cited above, ne items of noncompliance were

identified.

411

356

- 6-

Section II

,

Prepared by J. Hughes

Revieweu by D.

W. Hayes, Chief

EngineerinF Support

Section 1

1.

Licensee Action on IE Bulletins and Circular - Un_its 1 and 2

The inspectoi reviewed the licensee's responses to IE Bulletins,

a.

as stated in Section I of this report.

b.

The inspector reviewed IE Bulletin Nos. 77-05,77-05A,

77-07, 7P-02 and 78-04.

Subsequent to the issue of these

five bulletins, IE Circular ho. 78-08, which includes all

of the information contained in these bulletins, was issued.

For tracking purposes, the bulletins are closed and future

inspection results covering these matters will be docu-

mented under Circular No. 78-08.

Open items described in IE Circular No. '8-08 are as follows

(440/79-04-02; %

'74-04-02).

(1) For connectors, the reviews of environmental prototype

test results are not complete;

(2)

For electrical penetrations, the licensee has not

accepted the final environmental and seismic test

results;

(3) For terminal blocks, the licensee has not accepted

test report Pen-TR-79-03 " Qualification Test Report

on Three Terminal Blocks for use in BWR Nuclear Power

Plants;"

(4) With regard to limit switches, the liceisee stated

that all Class IE switches located in the primary

containment will be seismically and environmentally

qualified for their application.

Supporting docu-

mentation will be made available for review.

The inspector also reviewed IE Bulletin No. 78-06.

The

c.

licensee had performed a systematic review ef the Perry

design and equipment specification and confirmed that tio

Cutler-Hammer Type M, DC Relays, Catalog No. D23 MD were

being installed in Class IE equipment,

No items of noncompliance were identified.

-7-

411

357

.

2.

Quality As~2rance Implementing Procedures Review - Electrical,

Units 1 and 2

The inspector reviewed the following Ernst-Comstock (E-C) QA/QC

procedures:

Cable Tray and Conduit Installation, E-C Procedure 4.3.1,

a.

dated Ncvember 11, 1978.

b.

Installation of Owner Furnished Class lE Switchgear, E-C

Proced :e 4. 3.4, dated liarch 6,

1979.

c.

Fielo Instructions - Wire and Cable Receipt, handling and

Issuing, E-C Procedure 4.3.16, dated February 12, 1979.

d.

Raceway Installation, Cable Pulling and Cable Termination,

Cards Procedure, E-C Procedure, 4.3.17, dated April 14, 1979.

e.

Meggering, Hipot and Continuity Testing, E-C Procedure,

4.3.18, dated April 3, 1979.

f.

Sh!.mming Procedure for Switchgear, Unit Substations and

MCC's, E-C Procedure 4.3.19, dated March 15, 1979.

(g)

Installation of Low and Medium Motors, E-E Procedure,

4.8.13, dated October 26, 1978.

(h) Control and Calibration Checks of Specified Tools, E-C

Procedure, 4.9.1, dated April 1, 1979.

(1) Requisitioning for Installation of Utility Furn:shed Class lE

Equipment, E-C Procedure 4.10.3, dated August 8, 1979.

No items of noncompliance were identified.

3.

Review of Electrical Contractor's Training Records

The inspector reviewed four QC inspectors training records to

determine if they were certified in accordance with E-C QA

Procedure 4.1.4, Qualification and Certification of QC Personnel

and ANSI N45.2.6.

The records reviewed indicated the QC inspectors

were properly qualified.

No items of noncompliance were identified.

4.

, Electrical Components - Observation of Work Activities

The inspector observed partial and completed work on the electrical

embedded duct banks for the Emergency Diesel Generator Building.

Duc,.

-8-

411

358

.

.

banks were installed in accordance with drawing D426-630,

Revision B and Concrete Placement, E-C Procedure, 4.3.14, dated

April 11, 1979.

They were identified as DR-DG-FOST IB1, 2B1, 3B1,

4B1, SBl and 6B1 for documentation purposes. Nonconformance

Report (NR) CQE 45, dated April 9, 1979 was written against

2B1 and SBl due to interference with toe fuel oil pipe lines

running beneath the duct runs.

The inspector reviewed E-C docu-

mentation packages for the above mentioned duct banks.

No items of noncompliance were identified.

5.

Othcr Areas Inspected

a.

The inspector toured the plant site; including the electrical

contractor's cable reel yard, laydown area and the in-place

storage of switchgear components and found these areas in

accordance with procedures and specifications

b.

The inspector reviewed CEI's site procedures

he direction

of Fire Brigade and Cutting and Welding activities,

c.

During this inspection, the inspector also reviewed several

American Nuclear Insurers inspection reports of fire

protection safety discrepancies and recommended corrective

actions.

CEI was correcting the discrepancies identified

by the American Nuclear Tnsurers.

No items of noncompliances were identified.

Exit Interview

The inspectors met with licensee representatives (denoted under Persons

Contacted) at the conclusion of the inspection on April 20, 1979.

The

inspectors summarized the purpose and findings of the inspection.

The

licensee acknowledged the findings reported herein.

411

359

-9-