ML19225A306

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-395/79-10 on 790320-23.Noncompliance Noted: No Requirements on Weld Profile
ML19225A306
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 05/04/1979
From: Blake J, Conlon T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19225A200 List:
References
50-395-79-10, NUDOCS 7907180801
Download: ML19225A306 (7)


See also: IR 05000395/1979010

Text

.

..

LINITED STATES

n RECOq

,(g

jo,,

NUCLEAR REGULATORY COMMISSION

R EGloN 11

2

$

(

o

0

-

/!

101 M ARIETT A STR E ET, N.W.

'

ATLANTA, GEORGIA 30303

'I

g

o

Report No. 50-395/79-10

.

South Carolina Electric and Gas Company

Licensee:

Columbia, South Carolina 29218

Facility Name: Virgil C. Summer

License No. CPPR-94

Inspection at 9 -

Site near Columbia, South Carolina

_

SNM9

Inspector:

/ ~ ' '

Date Signed

J. J/ B1 te

fl) /~

/ /

g* ,

) n,n nm , V) j m-

5/ ///9

i

i

1

~ 7j, Conlon , ' Won Chief, RC&ES Branch

<I)4te Signed

Approved by:

T.'EN

Inspection on March 20-23, 1979

Areas Inspected

This routine, unannounced inspection involved 28 inspector-hours onsite in

the areas of Licensee Action on Frevious Inspection Findings, RCPB Piping-

Work and Work Activities; RCPB Piping-Quality Records;

RCPB piping Welding-

Work and Work Activities; RCPB Piping Welding-Review of Quality Records;

Licensee Identified Item - Potential 50.55(e), Cable Tray Support, unauthor-

ized weld.

Results

Of the 6 areas inspected, no apparent items of noncompliance or deviations

were identified in 5 areas; an apparent item of noncompliance was found in

one area (Infraction - No requirements on weld profile

paragraph 7).

.

.

7 907184 't

3g

ggg

.

-

.

DETAILS

1.

Persons Contacted

.

Licensee Employees

  • D. Moore, Director Surveillance Systems
  • A. A. Smith, Site QA Coordinator
  • H. Radin, Senior Engineer
  • J.

Algar, Site Manager

  • 0. S. Bradham, Manager - Operations
  • T. A. McAlister, QA Surveillance Specialist
  • C.

C. Turrett, QC Supervisor

  • E. Evans, QA Supervisor

J. Gypin, QA Surveillance Specialist

Other licensee and contractor employees contacted included several

construction craftsmen and inspectors.

Other Organizations

Daniels Construction Company (DCC)

  • J. Harvey, Construction Manager
  • G. Curtis, Mechanical QC Supervisor

M. Pierce, QC Supervisor

K. Heaton, QC Engineer

Gilbert Associates, Inc. (GAI)

R. H. Fleming

  • Attended exit interview.

2.

Exit Interview

The inspection scope and findings were summarized on March 23, 1979,

with those persons indicated in paragraph I above. The inspector

reviewed the scope and findings of the inspection. The details of how

the item of noncompliance evolved from the unresolved item No. 79-03-02

a

was discussed.

3.

Licensee Action on Previous Findings

,

a.

(Closed) Unresolved Item 50-395/78-04-02: Welds to be radiographed.

The inspector reviewed the additional radiographs taken of weld

FW-3 on ISO SP-09 and FW-14 on ISO CS-04.

These reshots were

com,,ared to the original radiographs for differences in technique

j d <,

I

I

_.

_ _ _ _

,

,

..

.

-2-

and resolution of the questions raised during the initial radio-

graph review.

The apparent questionable indications noted during

the original review have been resolved. This item is closed.

b.

(Closed) Unresolved Item 50-395/78-15-01, Cold Spring Requirements.

,

The inspector verified that the licensee's cold spring requirements

are described in specification SP-220-044461-000 Revision 3, Work

Procedure WP-VII-09 Revision 7, and Quality Control Procedure

QCP-VII-09 Revision 5.

This item is closed.

c.

(Closed) Noncompliance 50-395/79-03-01, Failure to Follow Tape

Procedures. The inspector held discussions with licensee and

Contractor personnel concerning the corrective actions stated in

the letter of response. The inspector concluded that SCE&G had

determined the full extent of the subject noncompliance, performed

the necessary survey and follow-up actions to correct the present

conditions and developed the necessary corrective actions to preclude

recurrence of similiar circumstances. The corrective actions

identified in the letter of response have been implemented.

d.

(Closed) Unresolved Item 50-395/79-03-02:

No Requirements on Weld

Profile.

The inspector reviewed results (records) of the visual

inspection performed on velds subject to the " flush" requirements

described in Table NB-3683.2-1 of ASME Section III (71S73). This

review disclosed that one of the field welds (FW-3), had not met

the " flush weld" profile requirement. The inspector stated that he

would close this matter as an unresolved item and would identify it

as a noncompliance. This matter is discussed under paragraph 7 of

this report.

4.

Unresolved Items

Uuresolved items were not identified during this inspection.

5.

Inspector Follow-Up Items

(Closed) Inspector Follow-up Item 50-395/78-16-03:

Surveillance Reports

Show Unacceptable Welds Accepted. The GAI Resident Engineer submitted

the final engineering evaluation on the welding of the electrical conduit

hangers and supports it accepts the welds "as - is".

The inspector

reviewed the inspection data and discussed the methods used to evaluate

the conditions noted with the resident engineer and the licensee. These

',

data vill be filed with the final resolution to the Corrective Action

,

Request CAR-39.

Note: The close-out of CAR-39 apparently resolves the

question of the acceptability of the we~lds which are supposed to be in

these hanger and support systsms. Arather problem with apparent

unauthorized welding in these same 'aanger and support systems has been

discovered by the licensee and is discussed in paragraph 6 of this

report.

346

052

.

.

..

.

-3-

6.

Licensee Identified Items

On March 23, 1979, the licensee informed the inspector that IE:II had

been notified of a possible 50.55(e) item concerning unauthorized weld

splicing of cable tray supports.

The licensee reported that information concerning unauthorized weldit e

of cable tray support No. 256 had been received from an anonymous worker

"ia a QC inspector intermediary.

Nondestructive Examination (NDE) of

1.he support revealed a spli e weld with apparent internal defects such

as lack of fusion and slag inclusions (the surface area was ground

smooth which made the weld very hard to locate).

Destructive testing

(i.e.

Tensile and Bend Tests) confirmed the lack of complete fusion and

the presence of lag in the weld. These test data were being forwarded

to the licen ne's A&E resident engineer for evaluation.

The licer.see stated that the anonymous worker had now volunteered to

come f orward this weekend (March 24-25, 1979) and lead SCE&G personnel

to the_ location of many more unauthorized splices.

The licensee stated that thej will keep the IE:II project inspector

informed of the status of the investigation.

The inspector reviewed the test data and inspected the samples used for

the destructive tests. There were no questions concerning the tests.

The inspector informed the licensee that this item would be assigned

inspector followup item number 50-395/79-10-02 for tracking purposes.

7.

Reactor Coolant Pressure Boundary Pipint (Welding I) - Observation of

Work and Work Activities

The inspector observed field welding of reactor coolant pressure boundary

(RCPB) piping at various stages of weld completion.

The applicable Code

for reactor Coolant pressure boundary piping is the ASME Foiler and

Pressure Vessel Code,Section III, 1971 Edition with Summer 1973 addenda

(71 & 73) as implemented by DCC QA Program for ASME work.

The inspector examined weld joint fitup prior to welding to deter-

a.

mine whether weld identification / location, joint preparation and

alignment, evidence of QC verification meet applicable procedures.

The following veld joints were examined:

-

Joint Number

Isometric

Svstem

Pine Size

,

FW-3 Repair

SE-Ril-09

Residuai lleat Removal (RIIR)

12-inch

b.

The inspector examined weld joints of pipe to pipe fitting (PPF)

and pipe to component (PC) where welding was beyond the root pass

to determiae weld / welder identification, qualified welder / weld

procedure, periodic checks of welding variables, use of specified

00

, ' '

.

-4-

weld material, proper interpass temperature, pre-heat, post-weld

heat treatment where applicable and, physical appearance of weld

starts, stops, undercut and surface inperfections).

(e.

g.

Joint Number

Size

Isometric No.

System

.

FW-2

3.5-inch

SE-RC-14

Feactor Coolant

FW-3

3.5-inch

SE-RC-14

Reactor Coalant

As stated in paragraph 3.d above, the record review disclosed that

field weld FW-3 (piping to pressurizer veld) had not met the " flush

weld" profile requirements, as described in Table NB'3683.2-1 of

ASME Section III (71, S73) and engineering specification

SP-220-044461-000 Revision 3, because tne internal pipe surface

(root of the weld) was inaccessible for grinding and/or inspection.

The inspector stated that since Table NB 3683.2-1 provides stress

indices for the analysis of piping systems with welds furnished in

the " flush" and "as-welded" conditions, it appears that FW-3 of the

pressurizer surge line should have been nonconformed and the design

engineers notified that the more conservative "as-welded" stress

indices be used for the analysis of this pipe section.

In addition, the inspector stated that the contractor's failure to

include special weld contour requirements in a written procedure

had resulted in a weld condition which was less conservative than

specified in the licensee's engineering specification SP-220-044461-

000 Revision 3.

The licensee agreed with the inspector's interpre-

tation of Table NB 3683.2-1 requirements and stated that a noncon-

formance report would be generated to inform the stress analysts

that the more conservative stress indices be used for that weld.

Failure to include acceptance criteria in written form is in This

noncompliance with Criterion V of Appendix B, to 10 CFR 50.

is considered to be an infraction and identified as item number

395/79-10-01: No requirements on veld profile.

8.

Reactor Coolant Pressure Boundary Piping (Welding II) Review of Quality

Records

The inspector reviewed the quality records described below relative to

RCPB pipe welding to determine whether these records reflected work

accomplishment consistent with NRC requirements and FSAR commitments.

The applicable code for this' welding is the ASME Boiler and Pressure

Vessel Code,Section III, Subsection NB, 1971 Edition with Addenda

through the summer cf 1973 as implemented by the DCC ASME QA Program.

Weld records for the. listed welds were reviewed in the areas of;

a.

.

visual and dimensiodal inspections, weld history, preheat and

030

a,a

.

  • * -

-

-5-

interpass temperature, NDE . weld repair, velder qualification and

inspector qualification, as opplicable to each weld:

Weld Number

ISO /Dwg. Number

Pipe Size

.

FW-7R4

SE-RH-09

12-inch

FW-2R1

SE-RH-09

12-inch

ew-6

SE-RC-14

3.5-inch

FW-7

SE-RC-14

3.5-inch

FW-3R1

SE-SI-22

6-inch

FW-6

SE-SI-22

6-inch

FW-6

SE-RC-14

3.5-inch

FW-6R1

SE-RH-09

12-inch

b.

The following velding material records relative to;

receipt inspec-

tion, weld material certification, issue and storage control, and

disposition of unused materials were reviewed:

(1) Welding material field requisitions No. 160837, No. 107774,

No. 146666, No. 162463.

(2) Certifications and receipt inspection records for:

E-308L-16, Lot No. 308LB22

E-308L-16, Lot No. 308LB43

ER-308L, Heat No. 01554

The inspector reviewed the following nonconformance reports (NCR)

c.

relative to RCPB pipe welding to determine whether records were

complete, legible, retrievable and properly closed out:

NRC Number

Subject

0570

Reactor Coolant - Base Metal Defect Adjacent

ts FW-6 on C-Loop Cold leg.

0557

Reactor Coolant - Grinding of Tacks on Thermal

Shield of Surge Line Nozzle.

0542

Reactor Coolant FW-6R1, Craft Bypassed QC&AI

Hold Points.

0538

Valve 1-8346 Check - Class II Valve Installed in

Class 1 System.

.

0517

Incore Instrumentation - Piping Dropped.

-

0516

Reactor Coolant FW-6R4, Porosity Ground Out

Without Authority

}!ib

b

.

-.

d- M eme h

..

.

.

.

.

-6-

Within the areas examined, there were no items of noncompliance or

deviations identified.

9.

Reactor Coolant Pressure Boundary Piping (I) - Observation of Work and

.

Work Activities

The inspector observed non-welding work activities for RCPB piping. The

applicable code for installation of RCPL piping is as shown in paragraph

7 of this report.

The following piping " runs" were inspected for compliance with instal-

lation specifications or plans:

From

To

Plan

Viive B702B

Valve 87elB

SE-RE-09

C.ld Leg Loop B

Valve 89,sB

SE-SI-22

Within the areas examined, there were no items of noncompliance or

deviations identified.

10.

Reactor Coolent Pressure Boundary Piping _ 'TI) - Review of Quality Records

The insprctor selected various RCPR piping components (e.g., pipe,

fittings and welded-in compone.cs) for review of pertinent records to

dete mine conformance with procurement, storage and installation speci-

fications and, QA/QC site procedures. A plicable requirements are

contained zu; I.icensee and contractor QA programs for ASME work.

Records of

t'- fol owing items were selected for review to ascertain

whether they (recards) were in conformance with applicable requirements

relative to the follocing areas: material test reports / certifications;

tendor supplied NDE reports; NSSS quality releases; site receipt

inspection; storage; installation; vendor nonconformance reports.

Item

System

Spool Piece 1-RC-04-01

12" Reactor Crolant

Valve 1-8702A

12" RHR

Spool Piece 1-51-22-02

6" Safety Inspection

Valve 1-h973B

6" Safety Inspect

4

.

Spool Piece 1-RH-09-05

12" RHR

Spool Piece 1-RC-14-03

3.5" Reactor Coolant

Spool Piece 1-RC-14-04 '

3.5" Reactor Coolant

Valve 1-8074C

3.5" Reactor Coolant

Within the areas examined, there were no noncompliances or deviations

identified.

-

-

. . -