Advises of Decision to Delay Scheduled Fuel Load Date to Nov 1980.Delay Caused by Plant Mods & Current Slippage of Project Schedule.Change in Date Will Be Included in Normal Monthly Schedule Rept
ML19225A196
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 07/12/1979
From: Wofford A
LONG ISLAND LIGHTING CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
SNRC-405, NUDOCS 7907180547
Download: ML19225A196 (2)


Text

.

gg,CO LONG ISLAN D LIG HTING COM PANY 4M JWO d4NTW 175 EAST CLD COUNTRY RCAO H I C K S v l L L E, NEW vCRK 11801 ANDaEw w *C rrC R O

-cc --c u c e SNRC-405 July 12, 1979 Mr. Harold R.

Denton Division of Nuclear Reactor Regulation U.S.

Nuclear Regulatory Commission Washington, D.C.

20555 Shoreham Nuclear Power Station - Unit 1 Docket No. 50-322

Dear Mr. Centon:

As a result of a recent cost and schedule analysis, we have determined that our scheduled fuel load date will be delayed five months to November 1980.

The reasons for this delay in our schedule are as follows:

1.

The project is currently two months behind schedule, and we can see no possibility of making up this current slippage.

2.

We have assessed the impact of certain plant modifications which will be required along with system modifications based on experience at operating plants, and on the recommendations of General Electric and certain other vendors.

We believe that the new fuel load date of November 1980 is a realistic target which we will meet.

However, I would like to emphasize that we have not taken into account any licensing delays which may be incurred as a result of the suspension of the NRC review of Shoreham because of Three Mile Island priorities.

The critical path to the operation of the Shoreham station, in our opinion, is the NRC Cperating License proceeding, and I would like to reemphasize our willingness to work with you in any manner possible to expedite the completion of the NRC review of Shoreham and the issuance of your Safety Evaluation Report (SER).

os o

42$3o

\\

GZ-t 3a6 042 t9071865W

  • LONG ISLAND LIGHTWG COM PANY Mr. Harold R.

Denton July 12, 1979 The change in our fuel load date, along with attendant changes in other major milestone dates, will be included in our normal monthly schedule report to the NRC.

Very truly yours, A.

W.

Wofford Vice President 346 043

.