Responds to NRC Requesting Addl Info to Evaluate SEP Topic VI-1, Organic Matl & Post-Accident Chemistry
ML19224D771
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 07/12/1979
From: Hoffman D
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Ziemann D
Office of Nuclear Reactor Regulation
References
TASK-06-01, TASK-6-1, TASK-RR NUDOCS 7907170024
Download: ML19224D771 (2)


Text

4 consumers (e

power Company nD l

oeme,s emeces 2Q West Mec hegan Avenue,,Jac kson, Mac higan 40201 e Area Code 517 788-0550 July 12, 1979 Director, iiuclear Reactor Replation Att Mr Dennis L Zi2: ann, Chief Operating Resetors Branch ;;c 2 U3 :iuclear Regulatory Iannission

'4ashington, DC 20555 DOCKET 50-155 - LICriSE DPR BIG ROCK POI:IT PLET - SEP TCPICG V1-1, "CRGA:iIC MATERIALS A:iD PCST-ACCIDE:iT CHE"ISTRY" A'iD VI-5, "CCMBUSTIELE GAS CO;iTROL" Consumers Power Company v.s requested by letter dated Jur 6,1979 to prc71de 9

specific information concerning the subjea* cro *opics.

. e requestad infor-nation is provided as an attachment to +M s letter.

David ? Hoffman (Signed)

David P Hoffman Assistant liuclear Licensin6 Adninistrator CC JGKeppler, US:iRC 5., o 7 9 0 717 0Dg/

BIG ROCK FOI:IT PLAUT - RESPO:ISE TO REQUEST FOR ADDITIO:!AL I:lFORMATIO:I NEEDED TC EVALUATE TOPIC VI-1, "ORGAIIIC MATERIALS A:iD POST-ACCIDENT CHEMISTRY" 1.

Estimate the areas and thicknesses of the tajor protective coating systems inside containment, including aluminum and ninc base paints, epoxy paints, acrylic Jacquer, etc.

Response - 90,000 sq ft; 5 - 8 mils 2.

Indicate whether these coating systens and their methods of application were qualified according to the recontendations of Regulatory Guide 1.5h.

Response - Big Rock Point was constructea before the issuance of Regulatory Guide 1 5k; the coatings and application are rat qualified to Regulatory Guide 1 5h.

3 If not, describe the QA provisions which were used to assure proper appli-cation.

Response - None, however work vas done to an approved specification and, althoush no formal QA progran existed at the time BRP was constructed, the normal on-site reviews and inspections were done routinely.

h.

For coatings not qualified with Regulatory Guide 1 5h, describe the present condition of the coatings, including estimates of the amounts of flaking, peeling, cracking, bubbles, etc.

Response - Coatings that are deteriorating are, as a matter of course, removed and resurfaced. Generally the coatings are in very good condition.

5 Estimate the quantity of other miscellaneous coating caterials (such as on snubbers) not qualified according to Regulatory Guide 1.5h.

Response - This estination is included in the total given in Item 1.

6.

Estimate the types and amounts of other organic materials such as electrical insulation inside containment.

Response - Electrical insulation approximately 65 cu ft, other organic caterials estimated to be 100 cu ft.

7 In addition to the information described above for organic coating systeca, we vill need the following information with respect to the related Topic VI-5, " Combustible Gas Control:" Esticate the surface area and thickness of aluminum, sinc and galvanized steel inside containment.

Response - Aluminum - not including =aterial in the spent fuel pool; surface area estimated to be 700 sq ft and a volume of about 70 cu ft.

Galvanised steel - sinc coated - primarily ductvork and cable trays; surface area 3,hCO sq ft; no thickness has been estinated.

an*

c* T

//s G J ~