ML19224D030
| ML19224D030 | |
| Person / Time | |
|---|---|
| Site: | Crane |
| Issue date: | 06/01/1979 |
| From: | Riley B NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Grier B NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| References | |
| REF-SSINS-50-320, TASK-TF, TASK-TMM NUDOCS 7907100540 | |
| Download: ML19224D030 (1) | |
Text
.
ge %,
/
o UNITED STATES
[ %,c,
- NUCLEAR REGULATORY COMMISSION
- g ^%j.. [c REGION 11 0, p2 101 MARIETTA ST, N.V... SUITE 3100
%..% /...f ATLANTA, GEORGIA 30303 p
JUN 1 1979 u
SSINS 50-320 MEMORANDUM FOR:
B. H. Grier, Director, Office of Inspection and Enforcement, Region I THRU:
James P. O'Reilly, Director, Office of Inspection and Enforcement, Region II
[p, FRCM:
B. W. Riley, Project Inspector, Region II
SUBJECT:
REPORT OF ACTIVITIES AT THREE MILE ISLAND Arrived at TMI site initially at 2030 on 4/25/79 cccmenced initial badging, body count and orientation - left site at 2230.
4/26/79 Spent day shift in completion of checkin processing,in #2 Control Room in turnover process from departing inspector.
4/27/79 Performed day shift duty in #2 Control Room taking specific to data hourly and transmitting same via telephone to NRR and 4/29/79 IE Trailers onsite.
4/30/79 Scheduled day off due to shift change.
5/1/79 Commenced nominal 0000-0800 shift overlapping with departing IE Supervisor P. keliogg.
5/2/79 Continued night shift coverage as Acting IE Supervisor -
to maintained contact with other IE inspectors onsite and coordinated 5/10/79 their activities as appropriate.
Provided inputs to morning reports and updating of Preliminary Notification series.
Departed site finally at 0800 on 5/10/79.
Have no substantive ccmments on observations to make regarding licensee operations or IE/NRC operations at site considering the changing evoluticns.
kb\\'#
B. W. Riley, Proje t Inspector 2 5 9 2 9 8 Reactor Projects Section No. 1 cc: