Submits Written Record of 790402-11 Actions Re TMI Event: Worked on Sequence of Events & as IE Shift Supervisor
ML19224C976
Person / Time
Site: Crane 
Issue date: 05/16/1979
From: Warnick R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
TASK-TF, TASK-TMM NUDOCS 7907100390
Download: ML19224C976 (1)


Text

.--

f "IG O UNITED STATES f

NUCLEAR REGULATORY ;.O MMISSIO N y:

P ((

3 REGloN lli

~

4' j

7ss mooSEVELT RO AO a

pg cLEN ELLYN. ILLINOIS 60137 May 16, 1979

@A 6 MEMORAND1 FOR:

B. H. Grier, Director, RI THRU:

R. 7 eishman, Chief, Reactor Operations and Nuclear Support Branch FROM:

R. F. Warnick, Chief, Reactor Projects Section 2 SU3 JECT:

REPORT OF ACTIVITIES AT THREE MILF ISLMO I arrived at the Harrisburg, PA airport the evening of April 2, 1979, and at Trailer City about 9:30 p.m.

The balance of that shift and most of the folicwing shift was spent working on the sequence of events.

I left the site at about 6:30 p.m. on April 3.

I worked the 4:00 pm to midnight shift starting on Apcil 3 and each day including April 10.

The first four days were spent on the se-quence of events - reviewing charts, sequence of events typewriter output, react 1=eter data output, and helping to establish i=portant chronology milestones.

The remaindar of the days were spent func-tioning as an IE Shift Supervisor in the IE Trailer (t/8).

I returned to RIII en April 11, 1979.

The lice nsee's ef forts to organi::e Trailer City, provide f acilities, and supply the infor=ation requested by NRC were outstanding.

I did not spenc any time on the island so I have no cot =ent, on the licensees site opera tons.

I was surprisec.o find that NRP. had assumed (or been given) the lead role in directing NRC's onsite efforts following this significant ev%c Yot, and your people are to be co== ended for the good job you have done in responding to the event.

b y

R. F. Warnick, Chief Reactor Projects Section 2 cc: