Forwards Summary of Actions & Communications for Period 790328-0401 While Involved in NRC Response to TMI-2
ML19221A480
Person / Time
Site: Crane 
Issue date: 05/08/1979
From: Berlinger C
Office of Nuclear Reactor Regulation
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
TASK-TF, TASK-TMR NUDOCS 7905230067
Download: ML19221A480 (3)


Text

['.

4 UNITED STATES r

  • 's 4

NUCLEAR REGULATORY COMMISSION j

WASHINGTON, D. C. 20555 s?A E

g, v [f

  • ,,e4 k,M h b,131 U Docket Number:

50-320 MEMORANDUM FOR:

Dennis N. Crutchfield, Chief Administrative Support Branch, Program Support Staff, NRR FROM:

Carl H. Berlinger, Section Chief Reactor Safety Branch, D0R

SUBJECT:

RECORD OF ACTION, TMI-2 By memorandum dated 04/24/79, H. Denton requested a record of personnel engaged in the NRC response to the TMI incident.

Since I am not certain that my actions and/or communications are logged in the IRC.

The enclosed is a sumnary (to the best of my recollection) of the period 03/28/79 through 04/01/79.

ftL(j Of LL b r;f:-t

(.

Carl H. Berlinger, Section Chief Reactor Safety Branch Division of Operating Reactors Encl osure :

As stated i

163 127 x/\\

1. "

o -

(,

/

/t

t' ENCLOSURE Record of Actions Wednesday, 03/28/79 8:25 AM - Arrived at work and was told by V. Stello's office to report to IRC - incident of unknown significance at TMI-2.

9:15 AM - Arrived IRC. - remained there through the day with Stello, et al.

7:30 PM - Left IRC for home with instructions to prepare to leave for TMI in AM with R. Vollmer.

Replaced at IRC by T. Marsh and Roy Woods.

Thursday, 03/29/79 7:00 AM - Arrived Bethesda, made change in Travel arrangements (Rental Car) and proceeded to IRC for update.

10:30 AM - Left Bethesda with G. Mazetis and F. Ashe.

12.45 PM - Arrived at TMI Observation Center. Met with rest of R. Vollmer Team.

1:30 PM - Attended briefing presentation in Observation Center by J. Herbein giving pr;liminary accident scenario and plant status.

Dignitaries present included 3 Senators (G. Hart, et al) and 1 State Senator and 7 member NRC team.

3:00 PM - Went to Processing Center on island with Mazetis, Ashe and Scherling for meeting with P,. Wilson and G. Broughton of GPU to discuss plant scenario and plant status.

7:00 PM to AM - Worked in conference room at Motel with NRC team, put to-gether a consolidated event scenario.

Briefed Vollmer, and IRC team on assessment of accident.

Friday, 03/30/79 7:30 AM - Assembled at Observation Center.

Set up teams - one on island, one at Observation Center (I&E) to gather info to advise staff at IRC. Went to Island with Mazetis, Klingler, Scherling, Ashe.

163 128

-2 Morning - Meeting with I&E (O. Bechman). Meeting with George Kunder (operator).

Noon

- Return to Observation Center.

Denton, Stelio et at arrived by helicopter. Briefed new arrivals on plant status and accident scenario.

Afternoon - Returned to Processing Center on Island.

Meeting with R. Wilson (GPU).

5:0J PM - Returned to Observation Center. Briefed Denton & Stello (in green house).

10:00 PM - Returned to Motel.

Saturday, 03/31/79 7:30 AM - Arrived Observation Center, began processing to go to Island.

9:00 AM - Arrived Processing Center, set up communication link to trailer spent day responding to requests from Observation Center Trailer, with Lauben. Mazetis, Adensam, et at.

9:00 PM - Relieved by night shif t, returned to trailer for debriefing.

10:30 PM - Returned to Motel.

Sunday, 04/01/79 7:30 AM - Arrived Observation Center for briefing, processed onto Island.

9:30 AM - Arrived Processing Center.

Reviewed procedures.

9:30 PM - Relieved, returned to Observation Center for debriefing, returned to motel.

)hb