ML19211A955
| ML19211A955 | |
| Person / Time | |
|---|---|
| Site: | Fort Saint Vrain |
| Issue date: | 11/22/1979 |
| From: | PUBLIC SERVICE CO. OF COLORADO |
| To: | |
| Shared Package | |
| ML19211A954 | List: |
| References | |
| NUDOCS 7912210376 | |
| Download: ML19211A955 (2) | |
Text
.
THE FORT ST. VRAIN INITIAL APPROACH TO POWER TESTS (B-SERIES)
INTERIM REPORT 13 Report for Period Ending November 22, 1979 1637 123 7912210 3 76 Inr.erim Report 8 covering the 90 day period ending August 22, 1978, re-ported the completion of all tests up to 70% of plant load. Since the Nuclear Regulatory Commission did not release the plant for operation at power levels in excess of 70%, no further Initial Approach to Power Tests were performed during the 90 days ending Novecher 22, 1979.
The Fort S t. Vrain Nuclear Generating Station was accepted for commercial operation at 70% power by Public Service Company of Colorado on July 1,1979.
Future interim reports will report the results of any startup tests at power levels above 70%.
'GE FORT ST. VPE N INITIAL APPROACH TO POWER TESTS (B-SERIES)
INTERIM REPORT 13 Report for Period Ending November 22, 1979 s
9 1637 125 A
Interim Report 8 covering the 90 day period ending August 22, 1978, re-ported the completion of all tests up to 70% of plant load.
Since the Nuclear Regulatory Commission did not release the plant for operation at power levels in excess of 70%, no further Initial Approach to Power Tests were performed during the 90 days ending November 22, 1979.
The Fort St. Vrain Nuclear Generating Station was accepted for commercial operation at 70% power by Public Service Company of Colorado on July 1,1979.
Future interim reports will report the results of any startup tests at power levels above 70%.
1637 126