Responds to IE Bulletin 79-14, Seismic Analysis for As- Built Safety-Related Piping Sys. Special Insp for as-built Configuration Inappropriate Due to Early Stages of Const. In-process & Final Insp & Review Methods Will Be Used
ML19211A237
Person / Time
Site: Hope Creek  PSEG icon.png
Issue date: 11/01/1979
From: Martin T
Public Service Enterprise Group
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-79-14, NUDOCS 7912170234
Download: ML19211A237 (2)


Text

sm TI-e -

Thomas J. Martin Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 201/430-8316 Vice President Engineering and Construction November 1, 1979 Mr. Boyce H.

Grier, Director Of" ice of Inspection and Enforcement U.S.

Nuclear Regulatory Commission Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. Grier:

NRC IE BULLETIN NO. 79-14 SEISMIC ANALYSIS FOR AS-BUILT SAFETY-RELATED PIPING SYSTEMS NO. 1 AND 2 UNITS HOPE CP.EEK GENERATING STATION In reply to IE Bulletin No. 79-14 dated July 2, 1979, we offer the following response:

The NRC requires that we inspect all of Hope Creek Generat-ing Station's Units No. 1 and 2 safety related systems in action items 2 and 3.

Due to the small amount of piping and hangers installed and the lack of any piping systems completed, a special inspection for "as-built" configura-tions would be appropriate until the system piping is completed.

Our in process inspection, final inspection, and review methods are being exercised over the next several years of construction.

These inspection procedures are sufficiently similiar in method and intent to the program outlined in this NRC bulletin that a special inspection at this time would be redundant.

Revision I, dated July 18, 1979 Supplement 1, dated August 15, 1979, and Supplement 2, dated September 7, 1979 provide additional guidance for the inspection, review and identification of non-conformances in piping systems at Hope Creek.

Due to the early construction stages of pipe 1591 188 7 012170 2L3dt

.., a Mr. Boyce H.

Grier, Director 11/1/79 and hanger erection at Hope Creek, we feel the above reply satisfactorily addresses Revision 1, Supplement 1 and 2, and completely responds to IE Bulletin No. 79-14.

Should additional information be desired, we will be pleased to further discuss it with you.

Very truly yours, CC:

Office of Inspection and Enforcement Division of Reactor Construction Inspection Washington, D.C.

1591 189