Text
IMHtTHEAST IFFII. FRIES 3
- ." "'O,", TIC 'C"'
2n*rdnN coNNECTlCUT 06101
,l, ':=ra"CJ "
ami 666-69" L
L
- :, :: '""m'.t"'
7l November 20, 1979 Docket No. 50-245 Director of Nuclear Reactor Regulation Attn:
Mr. D. L. Ziemann, Chief Operating Reactors Branch #2 U. S. Nuclear Regulatory Commission Washington, D. C.
20555
Reference:
(1)
W. G. Counsi3 letter to D. L. Ziemann dated September 18, 1979.
Gentlemen:
Millstone Nuclear Power Station, Unit No.1 Startup Physics Testing Program for Cycle 7 Report In Reference (1), Northeast Nuclear Energy Company (NNECO) submitted information relevant to the Startup Physics Testing Program for Cycle 7.
The purpose of this letter is to correct certain information erroneously submitted in the referenced letter.
The following information should be substituted for that previously submitted:
The referenced report stated the Technicel Specification shutdown margin was 0.47% AK/K. As noted during the NRC Audit 79-24, October 2 to 5,1979, this is not technicalsy correct. Technical Specification, Paragraph 4.3.A.1 states the shutdown margin limit is 0.33% A /K and only in the Bases, K
Paragraph 3.3.A, Page B 3/4 3-1 is the cycle "R" value addressed. For Cycle 7, "R" is 0.14% 6K/K, therefore, "R" + 0.33% A K/K = 0.47% A /K as K
noted in the referenced report.
The NRC auditor recommended the NRC be informed of our correct shutdown margin limit, therefore, this letter amends the report to reflect the Technical Specification shutdown margin limit.
Very truly yours, NORTHEAST NUCLEAR ENERGY r.0MPANY
/
. t (M
~
W. G. Counsil Vice President 1502 015 96 p
1912oso