Confirms 790529 Request for Extension Until 790831 for Submittal of Interim Deficiency Rept Re Halvorsen Boiler & Engineering Co QA Program
ML19210B973
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 08/29/1979
From: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NUDOCS 7911130102
Download: ML19210B973 (1)


Text

.

bC

-; l>r t'

n j " U t [ j. ;* :

m

(.

L1 rn-l L. :. (e it :

  • _m l.

1 n.

. i lLLUMINATING 8LDG. e PUBLIC SQUARE e CLEVELAND. OHIO 44101 e TELEPHONE (216) 623-1350 m Mall ADDRESS:

P. o. BOX 5000 Dalwyn R. Davidson v!CE PRESIDENT SYSTE M ENGINE ERING AND CONSTRUCTION August 29, 1979 Mr. James G.;Keppler Director of Region III Office of Inspection and Enforcement United States Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE:

Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Significant Deficiency RE:

S & M Constructors, Inc.'s Quality Assuiance Program Relative to Control of S 6 M Subcontractor: The Halvorsen Boiler and Engineering Company

Dear Mr. Keppler:

The Interim Report regarding subject significant dericiency states the Final Report is scheduled to be in your office by June 1, 1979.

On May 29, 1979, we requested an extension to August 31, 1979.

Pursuant to the conversation of August 24, 1979, between Messrs. W. J.

Kacer of our office and Kavin Ward of your office, this is to confirm that an extension past August 31, 1979 is requested.

It is anticipated that the Final Report will be submitted by December 15, 1979.

Very truly yours, 3

JA r 1/ h h.

D. R. Davidson Vice President System Enginaaring and Construction ksz cc: Victor Stello, Director Office of Inspection and Enforcement United States Nuclear Regulatory Commission Washington, D. C.