Order Extending Completion Date of CPPR-40 from 730930 to 740701
ML19210B547
Person / Time
Site: Crane Constellation icon.png
Issue date: 10/05/1973
From: Anthony Giambusso
US ATOMIC ENERGY COMMISSION (AEC)
To:
Shared Package
ML19210B546 List:
References
NUDOCS 7911090522
Download: ML19210B547 (1)


Text

.-

(

S T,

METROPOLITAN EDISON COMPANY (Three Mile Island Nuclear Station, Unit 1)

DOCKET NO. 50-289 ORDER EXTENDING COMPLETION DATE Metropolitan Edison Company is the holder of Provisional Construction Permit No. CPPR-40 issued by the Commission on May 18, 1968, for the construction of Three Mile Island Nuclear Station, Unit 1, a 2535 megawatt (thermal) pressurized water nuclear reactor presently under construction at the Company's site on Three Mile Island, an island in the Susquehanna River, in Londonderry Township, Dauphin County, Pennsylvania.

On August 30, 1973, the Company requested an extension of the completion dates because of delays due to:

(i) the excavation and repair of the containment vessel ring girder, (ii) major reduction of the construction force to assure more effective management control, (iii) modification of the reactor vessel internals as a result of Oconee 1 experience, and (iv) time loss and cleanup effort following a tropical storm in June 1972. The Director of Regulation having determined that this action involves no significant hazards consideration, and good cause having been shown, the bases for which are set forth in a memorandum dated September 27, 1973, from R. C. DeYoung to A. Giambusso.

IT IS HEREBY ORDERED THAT the latest completion date t ar CPPR-40 is extended from September 30, 1973 to July 1, 1974.

FOR THE ATOMIC ENERGY COMMISSION Crigirnt 3;=2d 5')

6. GicmbtLJ A. Giambusso, Deputy Director for Reactor Projects Directorate of Licensing